A safety walk that produces a photograph and an owner is a safety programme. One that produces a signed sheet in a binder is paperwork. This list is organised by hazard category so a finding can be trended across weeks and jobs.

Items
12
Photos required
25

Who runs it

Site safety lead or superintendent, weekly, with the affected trade foreman present.

When in the schedule

Weekly at minimum, plus after any incident, near miss or significant change in the work.

The checklist

Every item, and the photo that proves it

The photo count on each row is what RTI would require before the item can be submitted. Copy the list as-is, or load it into RTI and let the gate enforce it.

01

Fall protection

  • Leading edges, openings and shafts protected

    Guardrails complete, covers secured and marked, nothing removed and left open.

    3 photos
  • Personal fall arrest in use where required

    Anchor points rated and used correctly, harnesses inspected and in date.

    2 photos
  • Roof and elevated work areas controlled

    Warning lines, monitors or rails in place per the plan for that area.

    2 photos
02

Access and equipment

  • Ladders correct type, condition and angle, and secured

    No damaged rails or rungs; extension above the landing where required.

    2 photos
  • Scaffold erected, inspected and tagged

    Current tag visible, planking complete, base plates and mudsills present.

    2 photos
  • Aerial lifts and equipment inspected and operated by trained users

    Daily inspection completed, no bypassed controls, guards in place.

    2 photos
03

Electrical and hazards

  • Temporary power protected and cords undamaged

    GFCI in use, cords out of walkways and standing water, no missing plates.

    2 photos
  • Hot work permits, fire watch and extinguishers in place

    Permit posted, watch present, extinguisher within reach and current.

    2 photos
  • Hazardous materials stored, labelled and documented

    Containers labelled, safety data available on site, secondary containment where needed.

    2 photos
04

People and housekeeping

  • PPE appropriate to the work being done

    Eye, head, hand and foot protection matched to the task, not the gate rule.

    2 photos
  • Walkways, stairs and egress clear

    Nothing stored in exit paths or on stair landings.

    2 photos
  • Previous findings closed with a correction photo

    Last week's open items reviewed on this week's walk and closed with evidence.

    2 photos

What usually sends this back

The failures are almost always the evidence, not the work

  • Findings recorded without a location, which makes repeat conditions invisible.
  • Corrections claimed on the spot with no closing photo.
  • The same hazard category recurring for a month with no escalation.

Run it with the Photo Gate

A checklist nobody can submit half-finished

Load this list into RTI, stick a QR tag on the area it covers, and the submit button stays locked until every mandatory item is answered and the 25 required photos exist. Approved walks roll into a branded turnover package with a tamper-evident record behind every line.

Submission state

Mandatory items answered12 of 12
Photos attached22 of 25
Submit locked — 3 photos missing

The gate is enforced on the server, so it holds even if the phone is offline when the walk happens.