Final inspection checklist for construction

The final walk is where a job either hands over cleanly or drags on for six weeks. What separates the two is almost always documentation: not whether the work is done, but whether it can be shown to be done.

Items
15
Photos required
25

Who runs it

GC project manager and superintendent, with the owner's representative and the design team.

When in the schedule

After the punch list is closed and before the owner takes beneficial occupancy.

The checklist

Every item, and the photo that proves it

The photo count on each row is what RTI would require before the item can be submitted. Copy the list as-is, or load it into RTI and let the gate enforce it.

01

Systems operational

  • Every mechanical system runs through its sequence

    Record the system responding, not just the thermostat setting.

    2 photos
  • Electrical distribution complete, labelled and tested

    Panel schedules accurate, devices operable, emergency and standby systems exercised.

    2 photos
  • Plumbing fixtures operate with no leaks

    Run every fixture, check below, verify hot water delivery time and temperature.

    2 photos
  • Controls and low-voltage systems commissioned

    Access control, alarm, data and AV verified as handed over, with credentials transferred.

    1 photo
02

Life safety

  • Egress paths clear, lit and hardware operable

    Walk every exit, test panic hardware, confirm door swings and closers.

    2 photos
  • Fire protection systems tested and tagged

    Test records available, devices in place, extinguishers mounted and current.

    2 photos
  • Emergency lighting and exit signage functional

    Test each unit on battery; photograph the illuminated state.

    2 photos
  • Accessibility features verified in the field

    Clearances, reach ranges, hardware and signage measured, not assumed from the drawings.

    2 photos
03

Finishes and cleanliness

  • Punch list closed with correction photos

    Every open item has a closing photo attached to the original entry.

    1 photo
  • Final clean complete, protection removed

    Glass, floors, fixtures and horizontal surfaces; nothing left in the ceiling plenum.

    2 photos
  • Exterior and site complete

    Paving, striping, landscaping, signage and drainage all in their final condition.

    2 photos
04

Documentation and handover

  • Turnover package assembled and delivered

    Inspection records with photos, test reports, warranties, O&M manuals and as-builts in one package.

    1 photo
  • Warranties started and durations recorded

    Start dates agreed in writing; equipment registrations submitted.

    1 photo
  • Owner training delivered and attendance recorded

    Who attended, on what systems, on what date — with the session recorded where possible.

    1 photo
  • Keys, credentials and spare parts transferred

    Signed transfer record for keys, access credentials, attic stock and specified spares.

    2 photos

What usually sends this back

The failures are almost always the evidence, not the work

  • Systems demonstrated verbally but never recorded operating.
  • Closeout documentation assembled from memory a month after the trades left.
  • Owner training delivered to whoever happened to be on site that day, with no attendance record.

Run it with the Photo Gate

A checklist nobody can submit half-finished

Load this list into RTI, stick a QR tag on the area it covers, and the submit button stays locked until every mandatory item is answered and the 25 required photos exist. Approved walks roll into a branded turnover package with a tamper-evident record behind every line.

Submission state

Mandatory items answered15 of 15
Photos attached22 of 25
Submit locked — 3 photos missing

The gate is enforced on the server, so it holds even if the phone is offline when the walk happens.