The vehicular traffic coating walks, in build order
Vehicular traffic coating Rough-in· Vehicular traffic coatingVehicular traffic coating rough-in inspection checklistDeck moisture, profile, cracks, joints and terminations verified before the membrane covers them7 items12 photosVehicular traffic coating Final· Vehicular traffic coatingVehicular traffic coating final inspection checklistCoats, thickness, aggregate broadcast, cure and detail coverage checked on the finished system7 items14 photosVehicular traffic coating Punch· Vehicular traffic coatingVehicular traffic coating punch checklistCloseout walk for bubbles, thin spots, delamination at cracks and detail touch-up at drains3 items5 photos
Where each walk sits in the schedule
- Vehicular traffic coating rough-in inspection checklistrough-in
- After the concrete has cured and been shotblasted, before priming, while cracks and terminations are still open and can still be routed and detailed. Run by: The coating foreman walking the deck ahead of the primer crew, or the GC's superintendent releasing each pour or bay for coating.
- Vehicular traffic coating final inspection checklistfinal
- After all coats are down and cured and any specified flood or spray test is complete, before the deck is striped and opened to vehicles. Run by: The GC's superintendent with the coating foreman, walking each completed bay before it opens to traffic.
- Vehicular traffic coating punch checklistpunch
- During closeout, after the coating has seen its first traffic and the first weather, which is when thin spots and detail failures show. Run by: The coating foreman on a callback, or the GC's superintendent closing deck punch items before turnover.
What most often sends vehicular traffic coating work back
- Coating applied over a deck that hadn't reached the moisture level the primer needs, so the base coat blisters off within weeks.
- Moving cracks skimmed over with base coat instead of being routed and pre-detailed, and they telegraph straight back through the wear course.
- Drains and the termination reglet left undetailed because the crew wanted to keep the spray running, leaving the edge open to water behind the membrane.
- Wet-film thickness never checked during application, so the base or wear coat comes in thin and the system wears through early at the drive lanes.
- Aggregate broadcast to refusal in the ramp but skipped in the flatter bays, leaving slick areas where the wear course has no grip.
- Deck opened to traffic before the top coat had fully cured, printing tire marks and picking up the coating at turns.
- Blisters ground off and patched at the surface while the trapped moisture that caused them is left in the slab, so they come back next season.
- Delamination reopening along a crack that was never routed, patched as a surface defect instead of being cut out and re-detailed.
Common questions
- Which vehicular traffic coating inspections do these checklists cover?
- Vehicular traffic coating rough-in inspection checklist (rough-in): After the concrete has cured and been shotblasted, before priming, while cracks and terminations are still open and can still be routed and detailed. Vehicular traffic coating final inspection checklist (final): After all coats are down and cured and any specified flood or spray test is complete, before the deck is striped and opened to vehicles. Vehicular traffic coating punch checklist (punch): During closeout, after the coating has seen its first traffic and the first weather, which is when thin spots and detail failures show.
- Who runs a vehicular traffic coating inspection?
- The coating foreman walking the deck ahead of the primer crew, or the GC's superintendent releasing each pour or bay for coating. The GC's superintendent with the coating foreman, walking each completed bay before it opens to traffic. The coating foreman on a callback, or the GC's superintendent closing deck punch items before turnover.
- What most often sends vehicular traffic coating work back?
- Coating applied over a deck that hadn't reached the moisture level the primer needs, so the base coat blisters off within weeks. Moving cracks skimmed over with base coat instead of being routed and pre-detailed, and they telegraph straight back through the wear course. Drains and the termination reglet left undetailed because the crew wanted to keep the spray running, leaving the edge open to water behind the membrane. Wet-film thickness never checked during application, so the base or wear coat comes in thin and the system wears through early at the drive lanes.
- Can I run these checklists in RTI?