Turnover & closeout
Closeout package
A closeout package is the organized body of documentation that demonstrates the project was built, inspected, and accepted according to the contract — the deliverable that lets the contract be formally closed and final payment released. It typically pulls together the punch list closed to zero, passed final inspections, the certificate of occupancy, warranties, as-built drawings, and lien releases. What must be in it is defined by the contract and the owner, so the specification governs the contents.
Why it matters
What proves it
The strength of a closeout package is traceability — each claim of completion tied to the evidence behind it. Final inspection sign-offs linked to the work they cover, punch items shown closed with photos, and warranties and as-builts filed against the right scope let the owner verify the record instead of taking it on faith.
Common mistakes
Leaving assembly to the last week, when the people who did the work have demobilized and the photos are scattered. Mixing up the closeout package the owner needs to accept the contract with the turnover package the operators need to run the building — related, but not the same document.
Checklists that put closeout package to work
Free, field-ready checklists, each with the photo every item needs before it can be submitted.
Related terms
- Turnover packageThe set of documents and records handed to the owner or operator so they can run and maintain the completed building.
- Punch listThe running list of incomplete or defective work a contractor has to fix before an area is accepted and closed out.
- Certificate of occupancy (CO)The document the building department issues confirming a completed building is code-compliant and legal to occupy.
- Substantial completionThe milestone where the work is usable for its intended purpose, even with minor punch items still open.
- RetainageA portion of each payment the owner withholds until the work is complete and accepted, as leverage to finish.
- Temporary certificate of occupancy (TCO)A time-limited AHJ approval to occupy a building, or part of it, while specific remaining items are finished.
Knowing the term is step one. Proving it is the job.
RTI holds the submit button until every mandatory item is answered and the photos are attached, then chains the record so it can be proven untouched later.