How to inspect masonry
Masonry gets inspected in place and in sequence, because each course covers the one below it. The reinforcement, grout, ties, and flashing that make the wall work are all buried as the wall goes up, so the inspection has to keep pace with the mason — you can't check cell grout after the wall is topped out.
For the mason's foreman on their own work and the GC's superintendent verifying reinforced and veneer masonry against the structural and architectural drawings.
Step by step
Verify units, materials, and the mix
Confirm the block or brick, mortar type, and grout match the submittals, and that materials are protected and dry. Check the mock-up if one was built — it sets the accepted standard for color, joint, and workmanship.
Check layout, coursing, and dimensions
Verify wall location, thickness, openings, and coursing against the drawings, and that the wall is plumb and level within tolerance. Bond pattern and joint dimension should match the approved mock-up.
Inspect reinforcement, dowels, and grout cells
Confirm vertical and horizontal reinforcement size, spacing, laps, and that dowels line up with the bars they splice. Verify which cells are to be grouted are clean of mortar droppings and that cleanouts are provided where required for high lifts.
Verify grouting and consolidation
Watch that grout lifts are placed and consolidated per the spec, and that grout fills the reinforced cells solid. Under-consolidated or bridged grout leaves voids around the very steel the wall relies on.
Check ties, anchors, and joint reinforcement
For veneer and cavity walls, verify tie type, spacing, and embedment, and that joint reinforcement is continuous and lapped. Ties are the only thing holding a veneer to its backup — missing or corroded ties are a life-safety issue.
Inspect flashing, weeps, and the cavity
Confirm through-wall flashing is continuous with end dams and lapped correctly, that weep holes are open and clear at the right spacing, and that the cavity and drainage plane aren't mortar-fouled. This is the wall's drainage — block it and it leaks.
Coordinate the special inspector where required
For engineered and reinforced masonry, confirm the special inspector observes reinforcement, grout, and any prism or mortar testing at the required frequency. The inspection keeps pace with the wall, not after it.
Document each lift before it's covered
Photograph reinforcement, cleaned cells, flashing, and weeps before grout and the next courses hide them, and log any nonconformance for disposition. The record has to be built as the wall is.
What gets missed
- Trying to verify grout and reinforcement after the wall is topped out, when nothing can be seen or fixed.
- Blocked or missing weep holes and mortar-fouled cavities that turn a drainage wall into a bathtub.
- Under-spaced or missing veneer ties — the failure that drops a veneer off its backup.
- Flashing without end dams or with reverse laps, so water tracks back into the wall.
- Skipping the mock-up comparison, then arguing about workmanship after half the building is laid.
Questions people ask
- When do you inspect reinforced masonry?
- As it's built, lift by lift. Reinforcement and cell cleanliness are verified before grouting, and grout placement is watched as it happens. Once a lift is grouted and the courses continue, that work is permanent.
- Why are weep holes and flashing such a big deal?
- Because a masonry wall is a drainage wall — water gets in and is meant to drain back out through the flashing and weeps. Block the weeps or reverse the flashing laps and the water has nowhere to go but into the building.
Standards behind it
Terms worth knowing
Checklists that make this a one-tap job
Free, field-ready checklists, each with the photo every item needs before it can be submitted.
Related guides
- How to inspect the building envelopeInspect the envelope as a system — air barrier, water-resistive barrier, flashing, transitions, and sealants — with the continuity and mock-up that make it perform.
- How to inspect structural steelInspect steel erection in order — anchor bolts, plumb and level, bolted and welded connections — against the erection drawings and the inspection plan.
- How to run a first-article inspection and mock-upInspect the first fabricated item or build the first full-scale assembly in full so the approved sample becomes the standard the whole run is judged against.
Reading the steps is one thing. Proving you walked them is the job.
RTI holds the submit button until every mandatory item is answered and the photos are attached, then chains the record so it can be proven untouched later.