Inspection process
Mock-up
Also called: mockup, sample panel, field mock-up
A mock-up is a full-size sample of a repeating assembly — an exterior wall section, a masonry panel, a bathroom, a window and flashing detail — built and approved before the crew runs it across the whole project. Once accepted, it stops being a sample and becomes the standard: the finished work has to match it. It settles arguments about "acceptable" before they can happen at scale.
Why it matters
A specification describes intent; a mock-up shows the actual result — the mortar color, the reveal, the flashing lap, the finish. Approving one gives the crew a physical target and gives QC something concrete to inspect against, instead of relitigating workmanship on every unit.
How it shows up on site
The mock-up is built early, walked by the architect and owner, marked up, corrected, and then formally accepted. Sometimes it stays standing on site as the reference for the duration; the initial phase inspection of the real feature is measured against it.
Standards it's verified against
Checklists that put mock-up to work
Free, field-ready checklists, each with the photo every item needs before it can be submitted.
Related terms
- First article inspectionA full inspection of the first produced or installed item against every requirement before the rest of the run is allowed to proceed.
- Initial phase inspectionThe second phase of control — inspecting the first representative portion of a feature to set the workmanship standard for the rest.
- Definable feature of workA discrete, separately inspectable task or segment of work with its own start, finish, and acceptance criteria within the QC plan.
- Hold pointA stop in the inspection and test plan where work cannot continue until a required party inspects and signs off the release.
- Witness pointA step where a party is invited to observe the work, but the crew may proceed if that party doesn't attend within the agreed notice.
- Preparatory phase inspectionThe first of the three phases of control — a before-work review of submittals, materials, and criteria for a definable feature of work.