Structural steel erection ITP

Steel erection moves fast: anchor bolts are buried, connections are torqued or welded, and decking or fireproofing covers the work almost as soon as it is complete. An ITP maps each activity to its acceptance criterion, the verification method, the responsible party and the record that proves it happened before the next trade covers it.

Items
10
Photos required
10

Who runs it

Erector's quality lead with the GC superintendent; special inspector present for bolting and welding verification where required.

When in the schedule

Issued before steel delivery; each row is signed as the corresponding activity is released, before decking, fireproofing or finishes advance.

The checklist

Every item, and the photo that proves it

The photo count on each row is what RTI would require before the item can be submitted. Copy the list as is, or load it into RTI and let the gate enforce it.

01

What each ITP row defines

  • Activity in erection sequence

    Discrete and observable: 'set column line B', not 'erect steel'.

    No photo
  • Acceptance criterion with a value and tolerance

    A measurable limit plus the drawing or spec it comes from, not 'per code'.

    No photo
  • Verification method and point type

    Visual, measured, tested or certified; marked as hold, witness, surveillance or review.

    No photo
  • Responsible party and the record produced

    Named role and the artefact: photo set, survey, test report, signed checklist.

    1 photo
02

Hold and witness points

  • Hold points before concealment

    Anchor bolt verification, pre-erection release, pre-deck connection signoff.

    2 photos
  • Witness points for bolting and welding

    Pretensioning and weld inspection observed by the responsible party with notice.

    2 photos
  • Release recorded before the next activity

    Dated signature and photo evidence captured before decking or fireproofing covers the work.

    2 photos
03

Records and closeout

  • Each row traceable to the piece or grid line

    Tie the record to the column, beam or panel mark, not just to the floor.

    1 photo
  • Test reports and certificates attached to the row

    Bolt tests, weld procedures and inspector reports filed with the ITP, not separately.

    1 photo
  • Completed ITP issued as part of the turnover package

    Every row signed, every hold point released, no open deficiencies.

    1 photo

What usually sends this back

The failures are almost always the evidence, not the work

  • Anchor bolt layout verified after columns arrive instead of before the pour, when it can still be corrected.
  • Bolt pretensioning recorded on a summary sheet with no photo of a marked connection.
  • Welding or bolting signed off retrospectively after decking or fireproofing has covered the connection.

Run it with the Photo Gate

A checklist nobody can submit half-finished

Load this list into RTI, stick a QR tag on the area it covers, and the submit button stays locked until every mandatory item is answered and the 10 required photos exist. Approved walks roll into a branded turnover package with a tamper-evident record behind every line.

Submission state

Mandatory items answered10 of 10
Photos attached7 of 10
Submit locked, 3 photos missing

The gate is enforced on the server, so it holds even if the phone is offline when the walk happens.

Common questions

What does this steel itp checklist cover?
10 items across 3 sections, covering what each itp row defines, hold and witness points, records and closeout. Each item spells out what the person walking the job is actually looking for, not just a box to tick.
Who should run this inspection?
Erector's quality lead with the GC superintendent; special inspector present for bolting and welding verification where required.
When in the schedule should this walk happen?
Issued before steel delivery; each row is signed as the corresponding activity is released, before decking, fireproofing or finishes advance.
Why does every item ask for a photo?
10 of the 10 items call for photo evidence. A checklist answer without the photo is a claim; the photo is what makes the record worth something in a dispute and lets a reviewer approve work without re-walking the job.
What most often fails a steel itp inspection?
Anchor bolt layout verified after columns arrive instead of before the pour, when it can still be corrected. Bolt pretensioning recorded on a summary sheet with no photo of a marked connection. Welding or bolting signed off retrospectively after decking or fireproofing has covered the connection.
Can I use this checklist in RTI?
Yes. Start a free RTI workspace, build this list as a checklist, and the Photo Gate holds the submit button until every mandatory item is answered and its photos are attached. Approved inspections roll into a branded turnover package with a tamper-evident audit trail.