There is no re-inspection after a pour. Everything on this list is either photographed before concrete covers it or it is gone. Run this walk with enough lead time that a correction does not cost you the truck.

Items
13
Photos required
23

Who runs it

Concrete foreman and the GC superintendent, with the special inspector where one is required.

When in the schedule

The day before placement, and again immediately before the first truck — conditions change overnight.

The checklist

Every item, and the photo that proves it

The photo count on each row is what RTI would require before the item can be submitted. Copy the list as-is, or load it into RTI and let the gate enforce it.

01

Subgrade and preparation

  • Subgrade compacted, proof-rolled and free of standing water

    Uniform bearing, no soft spots, no frozen or saturated ground.

    2 photos
  • Vapor barrier installed, lapped and sealed at penetrations

    Laps at the required width, tears repaired, sealed at pipes and at the perimeter.

    2 photos
  • Base material to the correct depth

    Measure it and photograph the measurement, not just the surface.

    1 photo
02

Formwork

  • Forms to line, grade and dimension

    Check diagonals for square, elevations against the benchmark, and the top of form against finish elevation.

    2 photos
  • Forms braced, tight and released

    Bracing adequate for the placement rate; joints tight enough to prevent paste loss; release agent applied.

    2 photos
  • Joint locations laid out as designed

    Construction, control and isolation joints marked before the pour, not decided during it.

    1 photo
03

Reinforcement and embeds

  • Bar size, spacing and lap lengths match the drawings

    Spot-measure spacing and lap length; photograph a tape in frame.

    3 photos
  • Cover maintained on all faces

    Chairs and spacers at the correct height and frequency; no bars resting on the vapor barrier.

    2 photos
  • Dowels, anchor bolts and embeds set, located and secured

    Verify against the current drawing revision; templates used where accuracy matters.

    3 photos
  • Sleeves and blockouts installed for other trades

    Walk it with the MEP drawings — a missed sleeve becomes a core drill.

    2 photos
04

Placement readiness

  • Mix design approved and matched to the ticket

    Check the delivered ticket against the approved mix before discharge.

    1 photo
  • Access, equipment and crew ready for the placement rate

    Pump or chute access clear, vibrators on site and working, finishing crew staffed.

    1 photo
  • Weather conditions and curing plan confirmed

    Hot- or cold-weather measures ready before placement, not improvised after.

    1 photo

What usually sends this back

The failures are almost always the evidence, not the work

  • Rebar cover verified by eye, with no photo of a chair or a measurement.
  • Embeds and sleeves confirmed against an outdated drawing revision.
  • Subgrade wet or disturbed by weather between the walk and the pour, with no second look.

Run it with the Photo Gate

A checklist nobody can submit half-finished

Load this list into RTI, stick a QR tag on the area it covers, and the submit button stays locked until every mandatory item is answered and the 23 required photos exist. Approved walks roll into a branded turnover package with a tamper-evident record behind every line.

Submission state

Mandatory items answered13 of 13
Photos attached20 of 23
Submit locked — 3 photos missing

The gate is enforced on the server, so it holds even if the phone is offline when the walk happens.