Special inspection checklists for the high-strength bolting, structural welding, cast-in-place concrete, soils & foundations, structural masonry and sprayed fireproofing walks: 6 free lists, 43 items and 77 photo requirements, each item naming what to look for and the photo that proves it.
The special walks, in build order
High-strength bolting· Special inspectionHigh-strength bolting special inspection checklistFastener assemblies, pre-installation verification, snug-tight and pretensioned.8 items14 photosStructural welding· Special inspectionStructural welding special inspection checklistProcedure and welder quals, fit-up, in-process and completed welds, NDT witness.8 items14 photosCast-in-place concrete· Special inspectionCast-in-place concrete special inspection checklistReinforcement, mix and batch verification, sampling witness, placement and curing.7 items13 photosSoils & foundations· Special inspectionSoils and foundations special inspection checklistBearing verification, engineered fill and compaction, deep-foundation installation.7 items13 photosStructural masonry· Special inspectionStructural masonry special inspection checklistMaterials and proportions, reinforcement and grouting, mortar and grout sampling.6 items11 photosSprayed fireproofing· Special inspectionSprayed fire-resistive materials (SFRM) special inspection checklistSubstrate condition, application, thickness and density, bond and patching.7 items12 photos
Where each walk sits in the schedule
- High-strength bolting special inspection checklisthigh-strength bolting
- At fastener delivery, before installation begins, and at each connection during and after tightening — before it is covered or coated. Run by: A third-party or owner's-rep special inspector for structural steel, alongside the erector's bolt-up crew.
- Structural welding special inspection checkliststructural welding
- Before welding starts (qualifications and fit-up), during welding for critical joints, and at completion before coatings or fireproofing. Run by: A third-party or owner's-rep welding inspector, coordinating with the fabricator or erector's welding crew.
- Cast-in-place concrete special inspection checklistcast-in-place concrete
- Before the pour (reinforcement and embeds), at delivery (mix verification and sampling), and during placement and curing. Run by: A third-party or owner's-rep special inspector for concrete, with the placing crew and the testing lab.
- Soils and foundations special inspection checklistsoils & foundations
- At subgrade and bearing exposure, during fill placement and compaction, and throughout pile or pier installation. Run by: A third-party or owner's-rep geotechnical/special inspector, with the earthwork or foundation crew and the testing lab.
- Structural masonry special inspection checkliststructural masonry
- At material delivery, during laying and reinforcement placement, and at each grout lift and sampling. Run by: A third-party or owner's-rep special inspector for masonry, with the mason and the testing lab.
- Sprayed fire-resistive materials (SFRM) special inspection checklistsprayed fireproofing
- After the structure is accepted and the substrate is ready, during application, and before the assembly is enclosed. Run by: A third-party or owner's-rep special inspector for fire-resistive materials, with the applicator.
What most often sends special work back
- Pretensioning claimed on a summary sheet with no photo of a marked or verified connection.
- Faying surfaces coated or contaminated on a slip-critical connection that called for a clean surface.
- Fastener assemblies mixed on site so the lot verified in pre-installation testing is not the one installed.
- Welder qualification expired or not current for the position and process actually used.
- Completed welds coated before the visual inspection and any required NDT were recorded.
- Fit-up gaps and pre-heat left unverified on joints that called for them.
- Reinforcement signed off after forms were closed, so cover and spacing could not be verified.
- Test specimens taken and cured without the inspector present to witness the sampling.
Common questions
- Which special inspections do these checklists cover?
- High-strength bolting special inspection checklist (high-strength bolting): At fastener delivery, before installation begins, and at each connection during and after tightening — before it is covered or coated. Structural welding special inspection checklist (structural welding): Before welding starts (qualifications and fit-up), during welding for critical joints, and at completion before coatings or fireproofing. Cast-in-place concrete special inspection checklist (cast-in-place concrete): Before the pour (reinforcement and embeds), at delivery (mix verification and sampling), and during placement and curing. Soils and foundations special inspection checklist (soils & foundations): At subgrade and bearing exposure, during fill placement and compaction, and throughout pile or pier installation. Structural masonry special inspection checklist (structural masonry): At material delivery, during laying and reinforcement placement, and at each grout lift and sampling. Sprayed fire-resistive materials (SFRM) special inspection checklist (sprayed fireproofing): After the structure is accepted and the substrate is ready, during application, and before the assembly is enclosed.
- Who runs a special inspection?
- A third-party or owner's-rep special inspector for structural steel, alongside the erector's bolt-up crew. A third-party or owner's-rep welding inspector, coordinating with the fabricator or erector's welding crew. A third-party or owner's-rep special inspector for concrete, with the placing crew and the testing lab. A third-party or owner's-rep geotechnical/special inspector, with the earthwork or foundation crew and the testing lab. A third-party or owner's-rep special inspector for masonry, with the mason and the testing lab. A third-party or owner's-rep special inspector for fire-resistive materials, with the applicator.
- What most often sends special work back?
- Pretensioning claimed on a summary sheet with no photo of a marked or verified connection. Faying surfaces coated or contaminated on a slip-critical connection that called for a clean surface. Fastener assemblies mixed on site so the lot verified in pre-installation testing is not the one installed. Welder qualification expired or not current for the position and process actually used.
- Can I run these checklists in RTI?
- Yes. Start a free RTI workspace and load any of the 6 lists (43 items in total). The Photo Gate holds the submit button until every mandatory item is answered and its photos are attached, and approved inspections roll into a branded turnover package with a tamper-evident audit trail.