Drywall inspection checklist

The drywall walk is really two walks: the one before board goes up, which is the last chance to see everything behind it, and the one after finishing, which decides whether paint will look right. Both belong in the record.

Items
12
Photos required
23

Who runs it

Drywall foreman and the GC superintendent; the pre-cover sign-off usually needs each rough-in trade to confirm.

When in the schedule

Pre-cover immediately before hanging. Finish inspection after final sanding, under the lighting the space will actually use.

The checklist

Every item, and the photo that proves it

The photo count on each row is what RTI would require before the item can be submitted. Copy the list as-is, or load it into RTI and let the gate enforce it.

01

Before board goes up

  • All rough-in trades signed off in writing

    Electrical, plumbing, mechanical, low voltage and fire protection each confirmed complete.

    2 photos
  • Insulation installed, complete and unfaced areas covered

    No gaps at plates, corners and around boxes; batts not compressed behind wiring.

    2 photos
  • Blocking and backing verified against the finish plan

    Last chance to add blocking for anything hanging on this wall.

    2 photos
02

Hang

  • Board type correct for the location

    Moisture- and abuse-resistant types where specified; correct thickness for the framing spacing.

    1 photo
  • Fastener spacing and depth correct

    Screws dimpled but not breaking paper; no missed studs; no fasteners in the field of a floating corner.

    2 photos
  • Joints staggered and gaps within tolerance

    End joints offset, cutouts tight to boxes, no gaps that will need filling with compound alone.

    2 photos
03

Rated assemblies

  • Rated walls built full height and continuous

    Board carried to deck where required, no interruptions above the ceiling line.

    2 photos
  • Penetrations firestopped with the listed system

    Photograph each penetration with the applied material before the ceiling closes.

    3 photos
  • Rated walls identified above the ceiling

    Permanent labelling at the required intervals so a future trade knows what it is cutting.

    1 photo
04

Finish

  • Finish level matches the specification for each area

    Agree the level per space up front; check with a light held close to the surface.

    2 photos
  • Corners, beads and transitions straight and tight

    No crowning, no bead exposed through the compound, consistent reveals at openings.

    2 photos
  • Surface ready for finish under final lighting

    Walk with the actual fixtures on; document what is accepted and what is on the punch list.

    2 photos

What usually sends this back

The failures are almost always the evidence, not the work

  • Board hung over an unsigned rough-in, so a later defect means cutting open finished wall.
  • Rated assemblies missing firestopping at penetrations that were photographed after the board went up.
  • Finish level disputed at paint because nobody agreed on it in writing beforehand.

Run it with the Photo Gate

A checklist nobody can submit half-finished

Load this list into RTI, stick a QR tag on the area it covers, and the submit button stays locked until every mandatory item is answered and the 23 required photos exist. Approved walks roll into a branded turnover package with a tamper-evident record behind every line.

Submission state

Mandatory items answered12 of 12
Photos attached20 of 23
Submit locked — 3 photos missing

The gate is enforced on the server, so it holds even if the phone is offline when the walk happens.