Framing is the last honest look at the structure. Once rock goes on, every connector, every notch and every missing block becomes an argument instead of a photograph. This walk is organised so the concealed conditions are captured before close-in.

Items
13
Photos required
27

Who runs it

Framing foreman, then the GC superintendent before the pre-drywall inspection is requested.

When in the schedule

After MEP rough-in and before insulation and drywall, so notching and drilling done by other trades is visible in the same walk.

The checklist

Every item, and the photo that proves it

The photo count on each row is what RTI would require before the item can be submitted. Copy the list as-is, or load it into RTI and let the gate enforce it.

01

Layout and structure

  • Walls plumb, straight and on layout

    Check with a level and a string line; note any bow that will telegraph through finish.

    2 photos
  • Bearing points stacked and supported to foundation

    Point loads carried down continuously; no bearing landing on unsupported floor sheathing.

    2 photos
  • Headers, beams and posts sized and installed as drawn

    Member size and ply count match the plan; full bearing at each end.

    2 photos
  • Engineered members installed per the manufacturer's detail

    Web stiffeners, hangers and hole locations follow the printed detail, not field judgment.

    2 photos
02

Connections and fastening

  • Every connector fully nailed with the specified fastener

    All holes filled, correct nail type and length, no roofing nails substituted.

    3 photos
  • Hold-downs and anchor bolts installed and tightened

    Correct spacing and embedment, washers present, nuts snug.

    2 photos
  • Sheathing nailing pattern correct at edges and field

    Edge spacing on shear walls, no overdriven nails breaking the face of the panel.

    2 photos
03

Penetrations and modifications

  • Notching and boring within allowable limits

    Walk the runs the plumber and electrician cut; anything oversized gets repaired and re-photographed.

    3 photos
  • Nail plates installed where lines are close to the face

    Protection at every bored stud within striking distance of a screw.

    2 photos
  • Fire blocking and draft stopping in place

    Concealed vertical and horizontal spaces blocked at the required intervals, including soffits and chases.

    2 photos
04

Blocking for what comes later

  • Backing installed for cabinets, counters and casework

    Continuous blocking at the correct height for every upper run and support bracket.

    2 photos
  • Backing for grab bars, handrails and wall-hung fixtures

    Every accessible location and every wall-hung item, including ones not yet in the field.

    2 photos
  • Backing for mounted equipment and displays

    Confirm the location against the furniture or equipment plan before the wall closes.

    1 photo

What usually sends this back

The failures are almost always the evidence, not the work

  • Studs notched or bored by a trade after framing signed off, with no re-walk.
  • Missing blocking for grab bars, cabinets and TV mounts, discovered after paint.
  • Connectors installed with the wrong or missing fasteners — a photograph would have caught it.

Run it with the Photo Gate

A checklist nobody can submit half-finished

Load this list into RTI, stick a QR tag on the area it covers, and the submit button stays locked until every mandatory item is answered and the 27 required photos exist. Approved walks roll into a branded turnover package with a tamper-evident record behind every line.

Submission state

Mandatory items answered13 of 13
Photos attached24 of 27
Submit locked — 3 photos missing

The gate is enforced on the server, so it holds even if the phone is offline when the walk happens.