Foundation inspection checklist
Everything above the foundation depends on decisions that get buried within a week. This walk follows the sequence from open excavation to backfill so each stage is photographed while it is still open.
- Items
- 12
- Photos required
- 28
- Built for
- General contractors
Who runs it
Concrete or foundation contractor with the GC; a geotechnical or special inspector where required.
When in the schedule
At open excavation, before each pour, and again before backfill. Three short walks, not one long one.
The checklist
Every item, and the photo that proves it
The photo count on each row is what RTI would require before the item can be submitted. Copy the list as-is, or load it into RTI and let the gate enforce it.
Excavation and bearing
- 2 photos
Excavation to design depth and dimension
Measure to the benchmark and photograph the reading, not just the hole.
- 2 photos
Bearing material as anticipated and approved
No fill, no organics, no soft or disturbed material at the bearing plane.
- 2 photos
Excavation dry, protected and safely sloped or shored
No water in the bottom; sides stable for anyone who has to work in it.
Footings
- 2 photos
Footing dimensions and step locations as designed
Width, depth and step heights measured against the plan.
- 3 photos
Reinforcement size, spacing, lap and cover correct
Bars supported off the ground; measure cover and photograph the tape.
- 2 photos
Dowels for walls and columns placed and secured
Correct location and projection; not pushed in after placement.
Walls and anchorage
- 2 photos
Wall forms to line, plumb and dimension
Diagonals checked, top of wall at the design elevation.
- 3 photos
Wall reinforcement and openings as detailed
Bars at the correct face, added reinforcement at openings, sleeves in place.
- 3 photos
Anchor bolts and hold-downs placed to spacing and embedment
Set with a template before the pour and photographed with a tape in frame.
Protection and backfill
- 2 photos
Damp-proofing or waterproofing applied and continuous
Full coverage to the required height, detailed at the footing joint.
- 3 photos
Foundation drain installed with filter fabric and free-draining stone
Pipe sloped to discharge, fabric lapped, stone clean and to the required depth.
- 2 photos
Wall braced and cured before backfill, backfill placed in lifts
Floor framing or bracing in place; no dumping the pile against a green wall.
What usually sends this back
The failures are almost always the evidence, not the work
- Bearing conditions accepted verbally with no photo of the open excavation.
- Anchor bolt spacing checked after the pour, when it can only be repaired.
- Backfill placed before the wall is braced or cured, cracking the wall.
Run it with the Photo Gate
A checklist nobody can submit half-finished
Load this list into RTI, stick a QR tag on the area it covers, and the submit button stays locked until every mandatory item is answered and the 28 required photos exist. Approved walks roll into a branded turnover package with a tamper-evident record behind every line.
Submission state
The gate is enforced on the server, so it holds even if the phone is offline when the walk happens.