Waterproofing inspection checklist
Waterproofing is the definition of concealed work: the moment it is doing its job, nobody can see it. The record made during installation is the only thing that will ever explain a leak, so build the walk around the details, not the field.
- Items
- 12
- Photos required
- 26
- Built for
- Subcontractors
Who runs it
Waterproofing applicator with the GC; a manufacturer's representative where the warranty requires one.
When in the schedule
Before backfill below grade, before topping or protection board on decks, and before tile or finish in wet areas.
The checklist
Every item, and the photo that proves it
The photo count on each row is what RTI would require before the item can be submitted. Copy the list as-is, or load it into RTI and let the gate enforce it.
Substrate
- 2 photos
Surface sound, clean, dry and cured to the required age
No laitance, no form release, no honeycomb left unpatched.
- 2 photos
Cracks, tie holes and voids repaired
Each repair photographed before it is covered.
- 1 photo
Cove and fillet formed at inside corners
Continuous, correctly sized, no gaps at the wall-to-slab joint.
Detailing before the field coat
- 3 photos
Reinforcement at corners, joints and transitions
Detail work done first, photographed before the field membrane covers it.
- 3 photos
Every penetration detailed individually
One photo per pipe, sleeve, drain and anchor — collars sealed and reinforced.
- 2 photos
Drains set at the low point and clamped correctly
Membrane carried into the clamping ring; weep holes clear.
Membrane and termination
- 2 photos
Applied at the specified thickness or lap width
Wet mil readings for liquid systems, lap width for sheet systems — record the number.
- 2 photos
Terminations sealed and mechanically secured where required
Reglet, bar or counter-flash at the top; nothing left with an open edge.
- 2 photos
Protection board or drainage layer installed before backfill
Full coverage, no punctures, no exposed membrane left in the sun.
Testing
- 3 photos
Flood test held for the required duration
Photograph the water in place, the depth marker, and the clock at start and end.
- 2 photos
Underside inspected during and after the test
Walk the space below during the hold, not only afterwards.
- 2 photos
Repairs re-tested and documented
A second test record for any area that failed the first.
What usually sends this back
The failures are almost always the evidence, not the work
- Flood test signed off with no photo of standing water and no recorded start and end time.
- Terminations at pipe penetrations detailed but never photographed individually.
- Backfill placed before the protection board walk, damaging the membrane invisibly.
Run it with the Photo Gate
A checklist nobody can submit half-finished
Load this list into RTI, stick a QR tag on the area it covers, and the submit button stays locked until every mandatory item is answered and the 26 required photos exist. Approved walks roll into a branded turnover package with a tamper-evident record behind every line.
Submission state
The gate is enforced on the server, so it holds even if the phone is offline when the walk happens.
Related checklists
See all 69 checklists — 614 items and 1031 photo requirements in total.