Free checklist
Rough-in plumbing inspection checklist
Plumbing rough-in is inspected on two things: does it hold, and does it drain. Everything else on this list exists so that a leak two years from now can be traced to a joint somebody can see in a photograph.
- Items
- 13
- Photos required
- 24
- Built for
- Subcontractors
Who runs it
Plumbing foreman; GC verifies before requesting the rough-in inspection.
When in the schedule
After framing, before insulation and drywall, with the test still on the system when the walk happens.
The checklist
Every item, and the photo that proves it
The photo count on each row is what RTI would require before the item can be submitted. Copy the list as-is, or load it into RTI and let the gate enforce it.
Supply
- 2 photos
Pipe material and size correct for each run
Match against the riser diagram; look for reductions that were never designed.
- 2 photos
Joints made correctly and visible for inspection
No joints buried behind blocking; every connection accessible while the wall is open.
- 2 photos
Pressure test held and both readings recorded
Photograph the gauge at the start and after the hold period, with the time recorded.
- 1 photo
Isolation valves installed where designed
Fixture and branch isolation present and reachable after finishes go on.
Drain, waste and vent
- 2 photos
Horizontal runs sloped continuously
Measure it. A level on the run and a photo of the reading beats a claim.
- 1 photo
Cleanouts installed and accessible after finish
Check the cleanout against the finish plan — not behind fixed casework.
- 2 photos
Venting complete and correctly connected
Every trap vented, no flat vents below the flood rim, connections above the required height.
- 2 photos
DWV test held with the water or air standing
Photograph the standing head or gauge, and the system still under test when the walk happens.
Support and protection
- 2 photos
Piping supported at required intervals with correct hangers
No sagging between supports; isolation where dissimilar materials touch.
- 2 photos
Protection plates where piping passes through framing
Every bore within striking distance of a fastener.
- 2 photos
Penetrations through rated assemblies sealed
Listed firestop applied and photographed before the ceiling or wall closes.
Fixture rough locations
- 2 photos
Rough-in heights and offsets match the fixture schedule
Check against the actual fixture cut sheets, including accessible-height requirements.
- 2 photos
Blocking and carriers installed for wall-hung fixtures
Carrier set and secured, blocking behind every wall-hung item.
What usually sends this back
The failures are almost always the evidence, not the work
- Test gauge photographed at the start of the test but never at the end.
- Slope claimed but never measured on the long horizontal run.
- Penetrations through rated assemblies left unsealed above the ceiling.
Run it with the Photo Gate
A checklist nobody can submit half-finished
Load this list into RTI, stick a QR tag on the area it covers, and the submit button stays locked until every mandatory item is answered and the 24 required photos exist. Approved walks roll into a branded turnover package with a tamper-evident record behind every line.
Submission state
The gate is enforced on the server, so it holds even if the phone is offline when the walk happens.
Related checklists
See all 69 checklists — 614 items and 1031 photo requirements in total.