Skip to content
RTI

Checklists by trade

4 lists · 22 items · 36 photos

Fire Protection inspection checklists

Fire Protection inspection checklists for the rough-in, pre-cover, final and preventive maintenance walks: 4 free lists, 22 items and 36 photo requirements, each item naming what to look for and the photo that proves it. Work is commonly verified against NFPA 13 and NFPA 25; the edition in force is the AHJ's call on each project.

Where each walk sits in the schedule

Fire Protection rough-in inspection checklistrough-in
After branch lines and mains are hung and before ceiling grid or drywall closes in, and before the AHJ rough-in inspection is called. Run by: The sprinkler foreman walking their own rough-in with the GC's superintendent.
Fire Protection pre-cover inspection checklistpre-cover
After the branch lines and mains are complete and hydrostatically tested, before ceiling tile or hard lid closes the space above. Run by: The sprinkler foreman with the GC's superintendent, releasing the area once the test is documented.
Fire Protection final inspection checklistfinal
After escutcheons and covers are installed and the system is charged, before final acceptance testing and turnover. Run by: The sprinkler foreman at trim-out, then the fire marshal or AHJ at final acceptance testing.
Fire Protection preventive maintenance checklistpreventive maintenance
Monthly and quarterly rounds per the maintenance schedule, with an annual full system test. Run by: The fire protection contractor or in-house fire life-safety tech on a scheduled inspection round.

What most often sends fire Protection work back

  • Head locations laid out to the sprinkler drawing but never checked against the actual reflected ceiling plan, so lights and diffusers land on top of heads.
  • Hanger spacing stretched past the allowed interval on long branch line runs.
  • Branch line sizing tags missing or illegible, making it impossible to verify pipe size against the hydraulic calc later.
  • Areas released for cover before the hydrostatic test pressure and duration are actually documented for that zone.
  • Sprinkler heads sitting closer to ductwork, beams or light fixtures than the required clearance, only visible from above before the ceiling closes.
  • Leaks found during test repaired but the area re-covered without a re-test being logged.
  • Spare head cabinet missing the wrench or short on the required spare heads and types.
  • Signage at valves and the riser missing or not matching the zone it actually controls.

Verified against

Families only, never clause numbers. Adoption varies by jurisdiction; confirm the edition your authority having jurisdiction enforces before you run a walk against it.

Common questions

Which fire Protection inspections do these checklists cover?
Fire Protection rough-in inspection checklist (rough-in): After branch lines and mains are hung and before ceiling grid or drywall closes in, and before the AHJ rough-in inspection is called. Fire Protection pre-cover inspection checklist (pre-cover): After the branch lines and mains are complete and hydrostatically tested, before ceiling tile or hard lid closes the space above. Fire Protection final inspection checklist (final): After escutcheons and covers are installed and the system is charged, before final acceptance testing and turnover. Fire Protection preventive maintenance checklist (preventive maintenance): Monthly and quarterly rounds per the maintenance schedule, with an annual full system test.
Who runs a fire Protection inspection?
The sprinkler foreman walking their own rough-in with the GC's superintendent. The sprinkler foreman with the GC's superintendent, releasing the area once the test is documented. The sprinkler foreman at trim-out, then the fire marshal or AHJ at final acceptance testing. The fire protection contractor or in-house fire life-safety tech on a scheduled inspection round.
What most often sends fire Protection work back?
Head locations laid out to the sprinkler drawing but never checked against the actual reflected ceiling plan, so lights and diffusers land on top of heads. Hanger spacing stretched past the allowed interval on long branch line runs. Branch line sizing tags missing or illegible, making it impossible to verify pipe size against the hydraulic calc later. Areas released for cover before the hydrostatic test pressure and duration are actually documented for that zone.
Which standards is fire Protection work verified against?
NFPA 13, published by the National Fire Protection Association; NFPA 25, published by the National Fire Protection Association. Adoption varies by jurisdiction. Confirm the edition your authority having jurisdiction enforces before you run a walk against it.
Can I run these checklists in RTI?
Yes. Start a free RTI workspace and load any of the 4 lists (22 items in total). The Photo Gate holds the submit button until every mandatory item is answered and its photos are attached, and approved inspections roll into a branded turnover package with a tamper-evident audit trail.