Free checklist
Window installation inspection checklist
Nearly every window leak is a flashing-sequence problem, and the sequence is only visible for about an hour per opening. Photograph each layer as it goes on and a callback three winters from now becomes a five-minute question instead of an exploratory demolition.
- Items
- 12
- Photos required
- 18
- Built for
- Residential builders
Who runs it
Window installer on their own work; the GC or builder verifies before the wall is wrapped and clad.
When in the schedule
Per opening, as the units are set — before the weather-resistive barrier is lapped over the head flashing.
The checklist
Every item, and the photo that proves it
The photo count on each row is what RTI would require before the item can be submitted. Copy the list as-is, or load it into RTI and let the gate enforce it.
Rough opening
- 2 photos
Opening sized, square and plumb
Correct shim space on all four sides; measure both diagonals and photograph the tape.
- 2 photos
Sill sloped or a sloped pan installed
Water leaving the opening toward the exterior, not sitting on a flat sill.
- 2 photos
Sill pan continuous with sealed corners and back dam
Corners sealed or preformed, back dam present, pan turned up at the jambs.
Setting and fastening
- 2 photos
Unit set plumb, level and square with even reveals
Check operation before fastening; a racked frame will never seal.
- 1 photo
Shims at the specified locations, not bearing on the pan
Shims under load points only, and never blocking the drainage path.
- 1 photo
Fastener type, length and spacing per the manufacturer
Photograph a fastened jamb before trim covers it.
Flashing sequence
- 2 photos
Jamb flashing lapped over the sill flashing
Bottom layer first, then jambs over it — shingle-style, every time.
- 2 photos
Head flashing installed and lapped by the barrier above
Barrier over head flashing, not under. This is the single most common defect.
- 1 photo
Sealant applied where required and omitted at the sill
Perimeter sealed except the drainage path at the sill, which stays open.
Operation and closeout
- 1 photo
Sash operates, locks and weatherstrips seal
Open, close and lock every operable unit; check the seal compresses evenly.
- 1 photo
Insulation or foam at the perimeter without bowing the frame
Low-expansion product, frame still square after curing.
- 1 photo
Glass undamaged and labels intact until handover
No scratches or edge chips; protective film left on through the dirty trades.
What usually sends this back
The failures are almost always the evidence, not the work
- Sill pan photographed after the unit was set, so the pan itself is invisible.
- Head flashing lapped under the barrier instead of over it, discovered after siding.
- Shims and fasteners hidden behind trim with no record of spacing or type.
Run it with the Photo Gate
A checklist nobody can submit half-finished
Load this list into RTI, stick a QR tag on the area it covers, and the submit button stays locked until every mandatory item is answered and the 18 required photos exist. Approved walks roll into a branded turnover package with a tamper-evident record behind every line.