Skip to content
RTI

Inspection process

Punch walk

Also called: punch list walk, snag walk

A punch walk is the physical walk through a finished or near-finished space where the owner's rep, the GC, and often the architect go room by room tagging what still isn't right. Every scratch, missing trim piece, unfinished paint edge, and dead outlet gets written up as a punch item with a location and a responsible trade. It is how the abstract idea of "almost done" becomes a concrete, assignable list.

How it shows up on site

The team walks with the drawings and a way to log items on the spot — tagging locations, describing the defect, and naming the trade that owns the fix. A good punch walk is systematic, not a wander: same direction every time, nothing skipped, each item pinned to where it actually is.

In RTI each punch item carries the photo that proves it, so the trade coming back to fix it sees exactly what and where, and the back-check has a before shot to close against.

Common mistakes

Walking too early — before a trade has finished — buries real defects under items that were never done yet, and the list loses credibility. The other trap is a vague write-up: "paint" with no location or description is an argument waiting to happen.

Knowing the term is step one. Proving it is the job.

RTI holds the submit button until every mandatory item is answered and the photos are attached, then chains the record so it can be proven untouched later.