Painting inspection checklist
Paint failures are almost always preparation failures, and preparation is invisible under the first coat. Capture the substrate and the conditions before the sprayer starts and the argument about who owns a peeling wall is already settled.
- Items
- 12
- Photos required
- 21
- Built for
- Subcontractors
Who runs it
Painting contractor; the GC verifies preparation before the first coat and finish at acceptance.
When in the schedule
Preparation before priming, conditions on each coating day, and acceptance under final lighting.
The checklist
Every item, and the photo that proves it
The photo count on each row is what RTI would require before the item can be submitted. Copy the list as-is, or load it into RTI and let the gate enforce it.
Surface preparation
- 2 photos
Substrate clean, dry and sound
No dust, grease or efflorescence; moisture within range for the substrate.
- 2 photos
Patches, repairs and caulking complete and sanded
Repairs feathered and spot-primed so they do not flash through.
- 2 photos
Protection and masking in place
Floors, hardware, glazing and finished surfaces covered before any spraying.
Conditions and materials
- 1 photo
Temperature and humidity within the product range
Record the readings on each coating day — a photo of the meter beats a memory.
- 2 photos
Products match the approved submittal
Photograph the can label; confirm sheen and system against the schedule.
- 1 photo
Approved mock-up or sample available for comparison
Colour and sheen compared against the accepted sample, not a chip.
Application
- 2 photos
Primer appropriate to the substrate and fully applied
Correct primer for drywall, masonry, metal or wood — not one primer for the job.
- 2 photos
Coats applied at the specified thickness with recoat times observed
Wet or dry film readings where specified; recoat windows respected.
- 2 photos
Coverage uniform with no holidays, runs or lap marks
Check at a low angle with a light; corners and cut lines are where it shows.
Acceptance
- 2 photos
Cut lines straight and edges clean
No bleed at trim, ceiling or colour changes.
- 2 photos
Finish inspected under final lighting
Walk with the installed fixtures on; document what is accepted.
- 1 photo
Attic stock delivered and labelled
Correct quantity, labelled by room and colour, stored where the owner will find it.
What usually sends this back
The failures are almost always the evidence, not the work
- Painted over dust or an unprimed patch, then blamed on the product.
- Applied outside the temperature or humidity range with no record of conditions.
- Finish accepted under work lights, rejected the day the real fixtures go on.
Run it with the Photo Gate
A checklist nobody can submit half-finished
Load this list into RTI, stick a QR tag on the area it covers, and the submit button stays locked until every mandatory item is answered and the 21 required photos exist. Approved walks roll into a branded turnover package with a tamper-evident record behind every line.
Submission state
The gate is enforced on the server, so it holds even if the phone is offline when the walk happens.