Trade walkthroughs
How to inspect a fire alarm system
A fire alarm system is life-safety scope: the record that matters is the acceptance test run by the licensed installer and witnessed by the AHJ, not a superintendent's walk. Your job on this walkthrough is narrower and still important — observe, verify against the approved shop drawings, and document that the rough-in and device install were done right, so nothing you could have caught earlier turns into a failed acceptance test later.
For the GC's superintendent and the QC manager documenting fire alarm rough-in and device install alongside the licensed technician — not a substitute for the NICET tech's testing or the AHJ's acceptance.
Step by step
Work from the approved shop drawings only
Verify the device layout, circuit routing and panel location against the AHJ-approved fire alarm shop drawings — never against a field guess. Any deviation gets logged and routed back through the fire alarm contractor, not fixed on the fly.
Check rough-in wiring and boxes
Confirm the initiating and notification circuits are the listed cable, run and supported per the approved drawings, with boxes set for each device location. Photograph the runs and boxes while the walls are open.
Verify device coverage and locations
Observe that smoke and heat detectors, pull stations, horns and strobes are placed and spaced as the approved drawings show, at the mounting heights they require, with nothing blocked by later trades' work. Note gaps for the contractor to address.
Confirm device mounting and finish
Devices should be mounted to their listed boxes, level and secure, not covered in drywall dust or painted over. Check that strobes and speakers are the right candela and orientation the drawings call for.
Document penetrations and firestopping
Every cable through a rated wall or floor needs the listed firestop system; log each penetration for the firestopping walk. This is a common miss that surfaces at the AHJ's life-safety inspection.
Observe and record the acceptance test
The licensed technician runs the functional acceptance test — device-by-device activation, notification, and monitoring — with the AHJ witnessing. Your role is to observe, record that it happened, and file the technician's certified test report, not to certify it yourself.
Assemble the documentation trail
Collect the approved drawings, the contractor's test and inspection reports, and your dated photos of rough-in and devices into one record. That package is what proves the work for the turnover set and the AHJ.
What gets missed
- Treating a superintendent's walk as the acceptance test — the required test is the licensed tech's, witnessed by the AHJ, and nothing else stands in for it.
- Devices painted over, dust-fouled or blocked by ductwork installed after the fire alarm rough-in.
- Cable penetrations of rated assemblies left un-firestopped until the life-safety inspection.
- Field changes made off the approved shop drawings without a revision routed back through the fire alarm contractor.
- No consolidated record, so the AHJ asks for a test report nobody kept a copy of.
Questions people ask
- Can our field walk certify the fire alarm system?
- No. Fire alarm is life-safety scope — the licensed installer runs and certifies the acceptance test and the AHJ signs off. Your walk observes and documents so the work is right before that test, and it never replaces it.
- When do we bring in the AHJ?
- The AHJ witnesses the fire alarm contractor's acceptance test once the system is complete and pre-tested; your rough-in documentation and photos support that inspection rather than standing in for it.
Terms worth knowing
Checklists that make this a one-tap job
Free, field-ready checklists, each with the photo every item needs before it can be submitted.
Related guides
- How to inspect a fire sprinkler systemObserve and document sprinkler rough-in and final — layout, hangers, heads and hydro test — while the licensed contractor and AHJ run the required hydrostatic and acceptance tests.
- How to inspect firestoppingInspect firestopping at every rated penetration and joint before cover: right listed system, right materials, full seal, documented photo-by-photo against the assembly.
- How to run commissioning at closeoutSupport the commissioning agent as they verify systems perform as designed — schedule the tests, get systems ready, and document the functional performance tests and issues.