Fire alarm rough-in inspection checklist

Fire alarm rough-in is the last time the work is fully visible. Once the cover inspection passes and the walls, ceilings and slabs close, every defect left behind becomes a demolition bill. This checklist walks the rough-in in the order the work goes in, with the photo each item needs before it gets buried. Work is commonly verified against NFPA 72, the applicable building code. Confirm the edition your authority having jurisdiction has adopted.

Items
5
Photos required
8

Who runs it

The fire alarm foreman walking their own rough-in, or the GC's superintendent at the pre-cover hold point.

When in the schedule

After back boxes and conduit are set and the circuits are pulled, before insulation, drywall and ceiling grid close in and before the rough-in inspection is called.

The checklist

Every item, and the photo that proves it

The photo count on each row is what RTI would require before the item can be submitted. Copy the list as is, or load it into RTI and let the gate enforce it.

01

Boxes and conduit

  • Back boxes secured, square and at the correct depth

    Box firmly mounted to framing and set to the finished wall or ceiling surface, no crushed or over-deep boxes at pulls, horns and strobes.

    2 photos
  • Conduit and sleeves supported and roughed to the device layout

    Raceway supported at the required intervals, stub-ups and sleeves landing at the device and panel locations on the plan.

    1 photo
02

Wire type and separation

  • Circuit cable is the specified type and gauge

    Cable jacket marking matches the type and gauge the design calls for on initiating, notification and signaling circuits.

    1 photo
  • Fire alarm wiring separated from line-voltage circuits

    Signaling conductors kept out of raceways and boxes shared with power, separation held where they run parallel.

    2 photos
03

Mounting heights

  • Device rough-ins set to the required mounting heights

    Strobe, horn, pull-station and manual-station boxes checked against the mounting height for that device before the finish covers them.

    2 photos

What usually sends this back

The failures are almost always the evidence, not the work

  • Device back boxes roughed to a stud line without checking the ceiling and reflected plan, so pulls and horns land off the required mounting height once the finish goes up.
  • Initiating and notification wiring run in the same raceway as line-voltage circuits, with the separation never verified before the walls close.
  • The wrong cable type pulled for the circuit, discovered after cover when it won't pass the acceptance walk.

Run it with the Photo Gate

A checklist nobody can submit half-finished

Load this list into RTI, stick a QR tag on the area it covers, and the submit button stays locked until every mandatory item is answered and the 8 required photos exist. Approved walks roll into a branded turnover package with a tamper-evident record behind every line.

Submission state

Mandatory items answered5 of 5
Photos attached5 of 8
Submit locked, 3 photos missing

The gate is enforced on the server, so it holds even if the phone is offline when the walk happens.

Verified against

Common questions

What does this fire alarm rough-in checklist cover?
5 items across 3 sections, covering boxes and conduit, wire type and separation, mounting heights. Each item spells out what the person walking the job is actually looking for, not just a box to tick.
Who should run this inspection?
The fire alarm foreman walking their own rough-in, or the GC's superintendent at the pre-cover hold point.
When in the schedule should this walk happen?
After back boxes and conduit are set and the circuits are pulled, before insulation, drywall and ceiling grid close in and before the rough-in inspection is called.
Why does every item ask for a photo?
8 of the 5 items call for photo evidence. A checklist answer without the photo is a claim; the photo is what makes the record worth something in a dispute and lets a reviewer approve work without re-walking the job.
What most often fails a fire alarm rough-in inspection?
Device back boxes roughed to a stud line without checking the ceiling and reflected plan, so pulls and horns land off the required mounting height once the finish goes up. Initiating and notification wiring run in the same raceway as line-voltage circuits, with the separation never verified before the walls close. The wrong cable type pulled for the circuit, discovered after cover when it won't pass the acceptance walk.
Can I use this checklist in RTI?
Yes. Start a free RTI workspace, build this list as a checklist, and the Photo Gate holds the submit button until every mandatory item is answered and its photos are attached. Approved inspections roll into a branded turnover package with a tamper-evident audit trail.