Trade walkthroughs
How to inspect tile work
Tile is unforgiving: a substrate that moves, a waterproofing lap that was skipped, or a thin-set coverage that was rushed becomes a cracked joint or a leak long after the crew is gone. This walkthrough follows the assembly from the substrate up, spending most of its attention on what happens before the tile is set, because that is where the failures are born.
For the tile foreman and the GC's superintendent verifying substrate, waterproofing and setting before the tile goes down, and the finished work before acceptance.
Step by step
Verify the substrate is right for tile
Confirm the substrate is the correct type, flat within the tolerance large-format or thin tile needs, sound, and free of movement and deflection. Tile is only as stable as what it is bonded to.
Check waterproofing and any crack isolation
In wet areas, confirm the waterproofing membrane is continuous, lapped and turned up correctly, with the flood test done and recorded where required. Where crack-isolation membrane is specified, verify it is in before any tile is set.
Inspect the setting bed and coverage
Check the mortar is the specified type, combed in one direction, with the coverage the assembly requires — pull a tile in an inconspicuous spot if coverage is in doubt. Hollow-sounding tile means the bed did not transfer.
Verify lippage, alignment and joints
Look down the plane of the tile for lippage within tolerance, consistent joint width, and true lines. Large-format tile shows every bit of lippage, so check it against the acceptance tolerance, not by feel.
Check grout, sealant and the finished surface
Grout should be full, uniform and cured, with sealant — not grout — in the movement and change-of-plane joints. The finished surface should be clean, free of haze, with no cracked, chipped or drummy tile.
What gets missed
- Setting tile over a substrate that is out of flat beyond what large-format tile can hide.
- Waterproofing skipped, un-lapped, or never flood-tested in a wet area before tile went down.
- Movement joints tiled over with hard grout, so the assembly cracks when it moves.
- Partial thin-set coverage that sounds hollow and lets the tile crack or debond.
- Lippage judged by feel instead of against the acceptance tolerance for the tile size.
Questions people ask
- Why is so much of a tile inspection before the tile goes on?
- Because the failures that matter — movement, a leak, a debonded tile — start in the substrate, the waterproofing and the setting bed, none of which can be inspected once the tile is set and grouted.
- How is thin-set coverage verified?
- By pulling a set tile in an inconspicuous area to see the actual mortar transfer against the coverage the assembly requires, and by sounding the field for the hollow spots that mean the bed did not make full contact.
Terms worth knowing
Checklists that make this a one-tap job
Free, field-ready checklists, each with the photo every item needs before it can be submitted.
Related guides
- How to inspect a flooring installationInspect a flooring install from the substrate up: moisture and flatness, prep, layout, adhesion and finish, with the readings and photos each stage needs.
- How to inspect painting and coatingsInspect painting and coatings from prep to final coat: substrate readiness, product and system, film build and coverage, and finish, with proof at each stage.
- How to inspect the building envelopeInspect the envelope as a system — air barrier, water-resistive barrier, flashing, transitions, and sealants — with the continuity and mock-up that make it perform.
Reading the steps is one thing. Proving you walked them is the job.
RTI holds the submit button until every mandatory item is answered and the photos are attached, then chains the record so it can be proven untouched later.