Tile and stone pre-cover inspection checklist

A tile and stone pre-cover inspection is the hold point before concealed work disappears behind the next layer. This checklist is built for that walk: verify, photograph, then release the cover, not the other way around. Work is commonly verified against ANSI A108 / A118, TCNA guidance. Confirm the edition your authority having jurisdiction has adopted.

Items
4
Photos required
9

Who runs it

The GC's superintendent with the tile foreman at each wet area, since the membrane and its test disappear permanently under the tile.

When in the schedule

After waterproofing is applied and slope is formed, before any tile is set over it — the flood test only counts if it is held before the assembly is covered.

The checklist

Every item, and the photo that proves it

The photo count on each row is what RTI would require before the item can be submitted. Copy the list as is, or load it into RTI and let the gate enforce it.

01

Waterproofing continuity

  • Membrane continuous, up walls and sealed at penetrations

    Continuous coverage with laps and corners detailed per the manufacturer, turned up the wall to the required height, sealed to the drain flange and around pipe and fixture penetrations.

    3 photos
02

Slope and drainage

  • Slope to drain formed before the finish setting bed

    Positive fall to the drain checked with a level across the floor, no flat areas or reverse pitch, pre-slope present under bonded pans.

    2 photos
03

Flood test

  • Flood test filled, held and observed before tile is set

    Water dammed at the drain and held for the specified duration, level marked at the start, ceiling and connections below checked dry at the end.

    3 photos
  • Movement joint locations marked per the layout

    Soft-joint locations marked at perimeters, changes of plane and over any existing joints in the substrate, so setters leave them open instead of grouting through.

    1 photo

What usually sends this back

The failures are almost always the evidence, not the work

  • Membrane stopped at the floor and never turned up the wall or sealed to the drain flange, so water tracks under the pan.
  • Pre-slope missing under a bonded pan, leaving a flat floor that holds water below the tile with nowhere to weep.
  • Flood test skipped or drained after ten minutes because the setters were waiting, so a slow leak is only found after handover.

Run it with the Photo Gate

A checklist nobody can submit half-finished

Load this list into RTI, stick a QR tag on the area it covers, and the submit button stays locked until every mandatory item is answered and the 9 required photos exist. Approved walks roll into a branded turnover package with a tamper-evident record behind every line.

Submission state

Mandatory items answered4 of 4
Photos attached6 of 9
Submit locked, 3 photos missing

The gate is enforced on the server, so it holds even if the phone is offline when the walk happens.

Common questions

What does this tile and stone pre-cover checklist cover?
4 items across 3 sections, covering waterproofing continuity, slope and drainage, flood test. Each item spells out what the person walking the job is actually looking for, not just a box to tick.
Who should run this inspection?
The GC's superintendent with the tile foreman at each wet area, since the membrane and its test disappear permanently under the tile.
When in the schedule should this walk happen?
After waterproofing is applied and slope is formed, before any tile is set over it — the flood test only counts if it is held before the assembly is covered.
Why does every item ask for a photo?
9 of the 4 items call for photo evidence. A checklist answer without the photo is a claim; the photo is what makes the record worth something in a dispute and lets a reviewer approve work without re-walking the job.
What most often fails a tile and stone pre-cover inspection?
Membrane stopped at the floor and never turned up the wall or sealed to the drain flange, so water tracks under the pan. Pre-slope missing under a bonded pan, leaving a flat floor that holds water below the tile with nowhere to weep. Flood test skipped or drained after ten minutes because the setters were waiting, so a slow leak is only found after handover.
Can I use this checklist in RTI?
Yes. Start a free RTI workspace, build this list as a checklist, and the Photo Gate holds the submit button until every mandatory item is answered and its photos are attached. Approved inspections roll into a branded turnover package with a tamper-evident audit trail.