Insulation performs to the quality of its installation, not the number on the bag. Gaps, compression and missing air sealing cost more performance than a grade change ever recovers — and all three are obvious in a photograph taken before the wall closes.
- Items
- 12
- Photos required
- 26
- Built for
- Residential builders
Who runs it
Insulation contractor, with the builder or GC verifying before drywall is delivered.
When in the schedule
After all rough-in is signed off and before board goes up.
The checklist
Every item, and the photo that proves it
The photo count on each row is what RTI would require before the item can be submitted. Copy the list as-is, or load it into RTI and let the gate enforce it.
Air sealing first
- 3 photos
Penetrations through the envelope sealed
Plumbing, electrical, mechanical and low-voltage holes at top and bottom plates.
- 2 photos
Rim joist and band sealed and insulated
Continuous seal at the sill and rim before the cavity is filled.
- 2 photos
Attic access, chases and dropped soffits sealed and blocked
Air barrier continuous across every dropped ceiling and chase before insulating over it.
Batt and blown installation
- 3 photos
Full cavity contact with no gaps, voids or compression
Six-sided contact; batts split around wiring and plumbing rather than stuffed behind it.
- 2 photos
Correct product and thickness for each assembly
Verify against the energy design — walls, ceilings and floors may all differ.
- 2 photos
Blown depth uniform with markers installed
Depth markers visible and readable; photograph a marker at the design depth.
Spray foam
- 3 photos
Thickness verified with a depth gauge
Multiple readings across the assembly, photographed with the gauge in frame.
- 1 photo
Substrate temperature and conditions within the product range
Record conditions at application; poor adhesion is usually a temperature story.
- 2 photos
Ignition or thermal barrier applied where required
Coverage complete in every space the barrier applies to, including attics and crawls.
Rated and specialty assemblies
- 2 photos
Acoustic assemblies built to the tested detail
Correct insulation type, and joints sealed where the rating depends on it.
- 2 photos
Vapor control layer on the correct side for the climate
Confirm against the design before it is covered — this is not a field decision.
- 2 photos
Clearances maintained at heat-producing equipment
Flues, recessed fixtures and appliance vents kept clear per their listing.
What usually sends this back
The failures are almost always the evidence, not the work
- Batts compressed behind wiring instead of split around it.
- Air sealing skipped at top plates and rim joists, where it matters most.
- Spray foam thickness claimed but never measured or photographed with a depth gauge.
Run it with the Photo Gate
A checklist nobody can submit half-finished
Load this list into RTI, stick a QR tag on the area it covers, and the submit button stays locked until every mandatory item is answered and the 26 required photos exist. Approved walks roll into a branded turnover package with a tamper-evident record behind every line.
Submission state
The gate is enforced on the server, so it holds even if the phone is offline when the walk happens.