Free checklist
Pre-drywall inspection checklist
The pre-drywall walk is the single most valuable inspection on a residential job, because it is the last time the whole assembly is visible at once. Run it as one list across all trades rather than four separate sign-offs that never line up.
- Items
- 11
- Photos required
- 20
- Built for
- Residential builders
Who runs it
Builder's superintendent, with each trade foreman available to correct on the spot.
When in the schedule
After every rough-in is complete and insulation is in, immediately before board is delivered.
The checklist
Every item, and the photo that proves it
The photo count on each row is what RTI would require before the item can be submitted. Copy the list as-is, or load it into RTI and let the gate enforce it.
Structure
- 2 photos
Framing corrections from the structural walk completed
Close out every open framing item with a correction photo before covering.
- 2 photos
No unauthorised notching or boring by rough-in trades
Walk each MEP run and check the members it passes through.
Rough-in
- 2 photos
Electrical rough-in complete and boxes at finish depth
Devices located against the final furniture and cabinet plan.
- 2 photos
Plumbing tested and still under test at the walk
Gauge readable in the photo, with the time noted.
- 2 photos
Mechanical duct sealed and condensate trapped
Seals visible before insulation covers them.
- 1 photo
Low voltage and future runs pulled
Data, AV and security runs in place — retrofitting these after finish is the expensive kind of change order.
Envelope and insulation
- 2 photos
Air sealing complete at plates, penetrations and rim
Every hole through the envelope sealed before insulation hides it.
- 2 photos
Insulation installed without gaps or compression
Full contact at all six sides of the cavity; batts split around wiring, not compressed behind it.
- 2 photos
Window and door flashing visible and correct
Sill pan and lapping visible from inside where the assembly allows.
Blocking and buyer selections
- 2 photos
Blocking installed for every wall-hung item
Cabinets, grab bars, handrails, mounted displays, shelving.
- 1 photo
Buyer-selected changes reflected in rough-in
Walk the current selection sheet against the wall in front of you.
What usually sends this back
The failures are almost always the evidence, not the work
- Trades sign off on different days, so the last one covers a defect created by the second-to-last.
- Photos taken of the pretty wall and not the mechanical chase.
- Buyer-selected changes not reflected in blocking, discovered at trim.
Run it with the Photo Gate
A checklist nobody can submit half-finished
Load this list into RTI, stick a QR tag on the area it covers, and the submit button stays locked until every mandatory item is answered and the 20 required photos exist. Approved walks roll into a branded turnover package with a tamper-evident record behind every line.
Submission state
The gate is enforced on the server, so it holds even if the phone is offline when the walk happens.