Dry-in

Dry-in is the milestone where a building is buttoned up against the weather: the roof underlayment is on, the water-resistive barrier and flashings are in, and window and door openings are sealed so rain stays out. It doesn't mean finished — it means dry inside, which is what lets insulation, drywall and finish trades start without their work getting rained on. Hitting dry-in cleanly protects everything the enclosure is about to cover.

Why it matters

Start interior work before the building is truly dried in and you're trapping water in assemblies that are about to be closed — wet framing, soaked insulation and mold behind finishes that look fine on the surface. Dry-in is the gate that protects every trade downstream of it.

What an inspector looks at

The check is that the whole weather envelope is actually continuous before finishes commit: roof underlayment lapped, water barrier sealed, flashings integrated and openings closed, with no gap left for water to find. It's the flashing, barrier and penetration details reviewed together as one drainage plane.

RTI is photo-gated, so dry-in is documented across the enclosure — roof, wall barrier and openings shot before interior work covers them, the proof that the building was dry before it was closed.

Knowing the term is step one. Proving it is the job.

RTI holds the submit button until every mandatory item is answered and the photos are attached, then chains the record so it can be proven untouched later.