A quarterly gas detection system round is short on purpose: it catches the wear items that fail between annual services. This checklist is sized for a tech with a phone. Every item says what to look at and the photo that proves the round happened. Work is commonly verified against IMC (mechanical code), the applicable building code, manufacturer's published instructions. Confirm the edition your authority having jurisdiction has adopted.
- Items
- 4
- Photos required
- 6
- Built for
- Subcontractors
Who runs it
The controls or mechanical tech on the quarterly round; the field observes and documents, calibration stays with the certified tech.
When in the schedule
Every quarter, because a sensor in a parking area or kitchen sits in dust, grease and moisture and drifts long before anyone smells the problem.
The checklist
Every item, and the photo that proves it
The photo count on each row is what RTI would require before the item can be submitted. Copy the list as is, or load it into RTI and let the gate enforce it.
Sensors and heads
- 2 photos
Each sensor located, clear and mounted at the right height for its gas
Heads unobstructed and undamaged, low for heavier-than-air refrigerant, in the breathing zone for CO, none painted or wrapped.
- 1 photo
Calibration-due status read at each sensor or the panel
Sensor life and calibration-due dates within range, none expired, any past-due head flagged for the tech.
Controller and alarms
- 1 photo
Panel in normal state with no active faults
Controller powered, no trouble or fault indication, alarm setpoints displayed, event log free of unresolved alarms.
Ventilation interlock
- 2 photos
Alarm signal drives the exhaust fan and dampers
On a simulated or test alarm the exhaust fan starts and makeup-air/relief dampers move to their ventilation position, audible/visual alarms activate.
What usually sends this back
The failures are almost always the evidence, not the work
- Panel showing a fault or a sensor past its calibration-due date that everyone had learned to ignore.
- A refrigerant or CO head painted over, wrapped, or mounted where a later remodel walled it off.
- The gas alarm no longer starts the exhaust fan or drops the makeup-air damper, so detection happens but nothing ventilates.
Run it with the Photo Gate
A checklist nobody can submit half-finished
Load this list into RTI, stick a QR tag on the area it covers, and the submit button stays locked until every mandatory item is answered and the 6 required photos exist. Approved walks roll into a branded turnover package with a tamper-evident record behind every line.
Submission state
The gate is enforced on the server, so it holds even if the phone is offline when the walk happens.
Verified against
Common questions
- What does this gas detection system quarterly checklist cover?
- 4 items across 3 sections, covering sensors and heads, controller and alarms, ventilation interlock. Each item spells out what the person walking the job is actually looking for, not just a box to tick.
- Who should run this inspection?
- The controls or mechanical tech on the quarterly round; the field observes and documents, calibration stays with the certified tech.
- When in the schedule should this walk happen?
- Every quarter, because a sensor in a parking area or kitchen sits in dust, grease and moisture and drifts long before anyone smells the problem.
- Why does every item ask for a photo?
- 6 of the 4 items call for photo evidence. A checklist answer without the photo is a claim; the photo is what makes the record worth something in a dispute and lets a reviewer approve work without re-walking the job.
- What most often fails a gas detection system quarterly inspection?
- Panel showing a fault or a sensor past its calibration-due date that everyone had learned to ignore. A refrigerant or CO head painted over, wrapped, or mounted where a later remodel walled it off. The gas alarm no longer starts the exhaust fan or drops the makeup-air damper, so detection happens but nothing ventilates.
- Can I use this checklist in RTI?
- Yes. Start a free RTI workspace, build this list as a checklist, and the Photo Gate holds the submit button until every mandatory item is answered and its photos are attached. Approved inspections roll into a branded turnover package with a tamper-evident audit trail.
Related checklists
2642 items and 4211 photo requirements in total.