Waterproofing

Waterproofing rough-in inspection checklist

Waterproofing rough-in is the last time the work is fully visible. Once the cover inspection passes and the walls, ceilings and slabs close, every defect left behind becomes a demolition bill. This checklist walks the rough-in in the order the work goes in, with the photo each item needs before it gets buried. Work is commonly verified against the applicable building code, manufacturer's published instructions. Confirm the edition your authority having jurisdiction has adopted.

The checklist

Every item, and the photo evidence it needs

The photo count on each row is what RTI would require before the item can be submitted. Work the list here and watch the gate hold, or load it into RTI and let it enforce the real thing.

01

Before application

  • Approved system submittal and details on site

    The approved product data and the manufacturer's details for terminations, penetrations and drains available to the crew, matching the material delivered.

    No photo
  • Temperature and weather within the product's limits

    Air and surface temperature read and compared to the manufacturer's application range, with no rain expected inside the product's cure window.

02

Substrate

  • Substrate clean, dry and within tolerance

    No standing water, mud, fins or voids; surface profile matches what the membrane system requires.

  • Cracks, joints and transitions pre-treated

    Detail coat, strip or sealant at cracks, cold joints and inside corners before the field membrane.

  • Substrate cure or moisture reading within the membrane's limit

    Concrete cure age, or a moisture meter reading on concrete, block or board, taken where the membrane goes and compared to the manufacturer's value, location noted.

  • Form tie holes filled flush before membrane

    Where the wall is cast concrete, every tie hole packed with the specified patching material and struck flush, no open cones or projecting tie ends.

    No photo
03

Membrane application

  • Membrane thickness or ply count matches the spec

    Wet mil gauge readings or ply count verified at multiple points per area, not just at the starting edge.

  • Laps oriented to shed water and rolled tight

    Side and end laps shingled in the drainage direction, no fishmouths, no unbonded edges.

  • Terminations and penetrations per the system detail

    Termination bars, counterflashings and penetration boots match the manufacturer's detail for that condition.

  • Drain flanges clamped or bonded to the membrane

    Where a drain sits in the membrane, it is carried onto the drain body flange and held by the clamping ring or bonded as the drain and membrane details show.

    No photo
  • Membrane fully bonded with no wrinkles, blisters or pinholes

    Sheets rolled flat with wrinkles and bridged inside corners cut out and patched; fluid-applied coats free of pinholes, blisters and thin spots.

  • Fresh membrane protected until it has cured or bonded

    Membrane shielded from rain, foot traffic and falling debris until the cure or bond time the manufacturer lists has passed.

04

Protection and drainage

  • Protection course or drainage board installed undamaged

    Full coverage with no torn or displaced sheets, membrane still visible and intact at the edges.

  • Drainage board carried down into the footing drain

    Where drainage board is used, it runs to the footing drain with the filter fabric on the soil side and lapped over the drain as the drawings show.

    No photo
  • Flood test or water test documented where specified

    Water level photographed at start and end of the test period, drains plugged and tagged, result recorded.

What usually sends this back

The failures are almost always the evidence, not the work

  • Membrane photographed after the protection course went on, so laps and terminations can never be verified.
  • Flood test logged as passed with no photos of the water level at start and end.
  • Penetrations sealed with a generic detail instead of the manufacturer's penetration detail.

Common questions

6 answers

What does this waterproofing rough-in checklist cover?
15 items across 4 sections, covering before application, substrate, membrane application, protection and drainage. Each item spells out what the person walking the job is actually looking for, not just a box to tick.
Who should run this inspection?
The waterproofing foreman walking each lift, or the GC's superintendent before backfill or tile is released.
When in the schedule should this walk happen?
Per lift and per area: after substrate prep, after membrane application, and after protection course, before anything covers the work.
Why do these items ask for a photo?
11 of the 15 items call for photo evidence, 20 photos in all. A checklist answer without the photo is a claim; the photo is what makes the record worth something in a dispute and lets a reviewer approve work without re-walking the job.
What most often fails a waterproofing rough-in inspection?
Membrane photographed after the protection course went on, so laps and terminations can never be verified. Flood test logged as passed with no photos of the water level at start and end. Penetrations sealed with a generic detail instead of the manufacturer's penetration detail.
Can I use this checklist in RTI?
Yes. Start a free RTI workspace, build this list as a checklist, and the Photo Gate holds the submit button until every mandatory item is answered and its photos are attached. Approved inspections roll into a branded turnover package with a tamper evident audit trail.

Run it with the Photo Gate

A checklist nobody can submit half-finished