Glazing final inspection checklist

Glazing final inspection is where the punch list is either short or expensive. This checklist walks the finished work the way an owner or AHJ will see it — devices on, systems running, everything labeled — with the photos that close the item instead of reopening it. Work is commonly verified against the applicable building code, manufacturer's published instructions — confirm the edition your authority having jurisdiction has adopted.

Items
7
Photos required
12

Who runs it

The GC's superintendent with the glazing foreman, walking finished elevations before the owner's punch walk.

When in the schedule

After glazing is complete and sealant has cured, before exterior lifts come down and before turnover walks begin.

The checklist

Every item, and the photo that proves it

The photo count on each row is what RTI would require before the item can be submitted. Copy the list as-is, or load it into RTI and let the gate enforce it.

01

Glazing and sealant

  • Glass free of damage, labels and spacers removed

    No chips, scratches or edge damage; temporary labels off; glass bite and edge clearance per the system.

    2 photos
  • Perimeter sealant continuous and tooled

    Full contact both sides, no voids or skips, backer rod at the correct depth behind the sealant.

    2 photos
  • Glass make-up matches the schedule per opening

    Tint, coating orientation and laminated or insulated build verified against the glass schedule, labels photographed before removal where required.

    1 photo
02

Operation and hardware

  • Operable units open, close, latch and lock

    Full cycle test on every operable sash, hardware adjusted, locks engaging without forcing.

    1 photo
  • Screens, restrictors and safety glazing marks in place

    Required safety glazing marks present at hazardous locations, screens fitted and undamaged.

    1 photo
03

Water testing

  • Field water test performed on a sample of openings

    Test run per the specified method on the agreed sample, interior side photographed during and after.

    3 photos
  • Any leaks traced, repaired and re-tested

    Leak path identified, repair photographed, re-test documented on the same opening.

    2 photos

What usually sends this back

The failures are almost always the evidence, not the work

  • Water test run on the easiest ground-floor window while the upper floors are never tested.
  • Sealant tooling checked from the lift on one elevation, skipped where access was awkward.
  • Operable sash tested once at handover rehearsal and never again after hardware adjustments.

Run it with the Photo Gate

A checklist nobody can submit half-finished

Load this list into RTI, stick a QR tag on the area it covers, and the submit button stays locked until every mandatory item is answered and the 12 required photos exist. Approved walks roll into a branded turnover package with a tamper-evident record behind every line.

Submission state

Mandatory items answered7 of 7
Photos attached9 of 12
Submit locked — 3 photos missing

The gate is enforced on the server, so it holds even if the phone is offline when the walk happens.

Common questions

What does this glazing final checklist cover?
7 items across 3 sections — glazing and sealant, operation and hardware, water testing. Each item spells out what the person walking the job is actually looking for, not just a box to tick.
Who should run this inspection?
The GC's superintendent with the glazing foreman, walking finished elevations before the owner's punch walk.
When in the schedule should this walk happen?
After glazing is complete and sealant has cured, before exterior lifts come down and before turnover walks begin.
Why does every item ask for a photo?
12 of the 7 items call for photo evidence. A checklist answer without the photo is a claim; the photo is what makes the record worth something in a dispute and lets a reviewer approve work without re-walking the job.
What most often fails a glazing final inspection?
Water test run on the easiest ground-floor window while the upper floors are never tested. Sealant tooling checked from the lift on one elevation, skipped where access was awkward. Operable sash tested once at handover rehearsal and never again after hardware adjustments.
Can I use this checklist in RTI?
Yes. Start a free RTI workspace, build this list as a checklist, and the Photo Gate holds the submit button until every mandatory item is answered and its photos are attached. Approved inspections roll into a branded turnover package with a tamper-evident audit trail.