Sewage lift station annual maintenance checklist

The annual lift station service is the deep pass: the measurements, cleanings and tests a quarterly round doesn't reach. This checklist keeps the full service on record with the photos that make it defensible later. Work is commonly verified against IPC / UPC plumbing codes, manufacturer's published instructions. Confirm the edition your authority having jurisdiction has adopted.

The checklist

Every item, and the photo evidence it needs

The photo count on each row is what RTI would require before the item can be submitted. Work the list here and watch the gate hold, or load it into RTI and let it enforce the real thing.

01

Notice and isolation

  • Operator and alarm receiver told the station is coming down

    Owner's operator and whoever answers the alarm told before pumps come out, and inflow held or a bypass pump or vacuum truck set up so the well can't overflow.

    No photo
  • Each pump locked out and tagged before it is pulled

    Power and control feeds, taken downstream of any transfer switch, locked, tagged and proven dead. To run it: pump seated, grate on, crew clear, own locks off, run, re-locked before hands go back in.

  • Gas monitor kept at the hatch for the whole pull

    Beyond the quarterly spot reading, the monitor stays at the open hatch with forced air where the plan calls for it, and work stops on any hydrogen sulfide or low-oxygen alarm.

  • Anyone below the hatch goes on a confined-space permit

    Permit issued before anyone enters, with the air tested, ventilation running, an attendant at grade, retrieval gear rigged and rescue arranged.

    No photo
02

Pump removal and rails

  • Pumps lifted on the guide rails and inspected

    Each pump raised on its rail from grade, impeller and seal checked, cutter or vortex clear of rags, reseated tight on the discharge base.

  • Guide rails and lifting chains sound

    Rails, brackets, chain and shackles checked for corrosion and wear, chain rated and not stretched, so a pump can be pulled without a fight.

  • Voltage and current per phase read on each reseated pump

    Beyond the quarterly amp check, every phase read under the energized-work procedure during the temporary release, imbalance noted, and each pump set against last year.

  • Pump-down rate timed against the station's baseline

    Each pump timed drawing the well between two marked levels with inflow noted, set against commissioning or last year's time to show impeller wear or a throttled valve.

    No photo
03

Valves

  • Check valves service and seat clean

    Each check valve opened and inspected, flapper or ball seats fully so the well doesn't backfill, no debris holding it open.

  • Isolation valves exercised and hold

    Each isolation valve fully stroked, not seized, so either pump can be isolated for service while the other stays in duty.

04

Wet well

  • Wet well cleaned out and floats cleared

    Grease cap and settled solids removed, floats and transducer cleaned and re-hung, done from grade or under an authorized entry permit.

  • Wet-well walls, benching and hatch frame inspected

    Concrete or liner seen from the hatch with a light for gas corrosion, exposed rebar, infiltration or broken benching, and the hatch hinges, hold-open and grate sound.

05

Return to service

  • Locks cleared and pumps back in auto

    Locks and tags removed by whoever hung them, grate and hatch closed, selectors in auto, and a full cycle run on each pump with the check valve holding.

  • Pumps proven to start on backup power where provided

    Coordinated with whoever runs the generator or transfer test, both pumps seen restarting and carrying the well on the standby source, then back on utility power.

    No photo
  • Alarm receiver told the station is back with readings logged

    Owner's operator and alarm receiver told the station is back in service, and amps, voltages, pump-down times and wet-well findings logged as next year's baseline.

    No photo

What usually sends this back

The failures are almost always the evidence, not the work

  • Guide rails and lifting chain corroded so a pump can't be pulled cleanly when it fails, turning a routine swap into an emergency.
  • Check valve stuck part-open, letting the well backfill each time the pump stops so the pumps short-cycle and burn out early.
  • Isolation valves seized, so a single pump can't be isolated for service without shutting the whole station down.

Verified against

Common questions

6 answers

What does this sewage lift station annual checklist cover?
15 items across 5 sections, covering notice and isolation, pump removal and rails, valves, wet well, and more. Each item spells out what the person walking the job is actually looking for, not just a box to tick.
Who should run this inspection?
The plumbing service crew on the annual visit, with a hoist and a confined-space permit where entry is authorized.
When in the schedule should this walk happen?
Once a year. Pumps are lifted on the guide rails from grade; any entry into the wet well runs under an authorized confined-space permit, not as a routine step.
Why do these items ask for a photo?
10 of the 15 items call for photo evidence, 12 photos in all. A checklist answer without the photo is a claim; the photo is what makes the record worth something in a dispute and lets a reviewer approve work without re-walking the job.
What most often fails a sewage lift station annual inspection?
Guide rails and lifting chain corroded so a pump can't be pulled cleanly when it fails, turning a routine swap into an emergency. Check valve stuck part-open, letting the well backfill each time the pump stops so the pumps short-cycle and burn out early. Isolation valves seized, so a single pump can't be isolated for service without shutting the whole station down.
Can I use this checklist in RTI?
Yes. Start a free RTI workspace, build this list as a checklist, and the Photo Gate holds the submit button until every mandatory item is answered and its photos are attached. Approved inspections roll into a branded turnover package with a tamper evident audit trail.

Run it with the Photo Gate

A checklist nobody can submit half-finished