The annual lightning protection system service is the deep pass: the measurements, cleanings and tests a quarterly round doesn't reach. This checklist keeps the full service on record with the photos that make it defensible later. Work is commonly verified against NFPA 780, the applicable building code. Confirm the edition your authority having jurisdiction has adopted.

Items
4
Photos required
6

Who runs it

The facilities lead documenting the visit while the qualified lightning protection inspector performs the periodic inspection.

When in the schedule

On the periodic cycle, scheduled with the inspector so the continuity checks and any findings are witnessed and recorded, especially after major roof work.

The checklist

Every item, and the photo that proves it

The photo count on each row is what RTI would require before the item can be submitted. Copy the list as is, or load it into RTI and let the gate enforce it.

01

Inspection observed

  • Inspector's continuity checks observed and recorded

    Watch the inspector check down-conductor continuity to ground, record which downleads were checked and the outcome the inspector reports.

    2 photos
  • Terminal, conductor and bond survey observed

    Inspector's survey of terminals, runs and bonds observed across the roof, deficiencies the inspector calls out photographed and listed.

    1 photo
02

Grounds and connections

  • Ground connections and test wells opened and observed

    Test wells opened with the inspector, connections examined for corrosion or looseness, condition the inspector reports recorded.

    2 photos
03

Findings and records

  • Inspection report filed and deficiencies assigned

    Inspector's report attached to the maintenance record, each deficiency given a follow-up owner and the next inspection date noted.

    1 photo

What usually sends this back

The failures are almost always the evidence, not the work

  • Inspector's findings left on the inspection report and never turned into work orders, so the same loose terminal shows up year after year.
  • Down-conductor continuity called good from a visual only, with the inspector's actual continuity check never observed or recorded.

Run it with the Photo Gate

A checklist nobody can submit half-finished

Load this list into RTI, stick a QR tag on the area it covers, and the submit button stays locked until every mandatory item is answered and the 6 required photos exist. Approved walks roll into a branded turnover package with a tamper-evident record behind every line.

Submission state

Mandatory items answered4 of 4
Photos attached3 of 6
Submit locked, 3 photos missing

The gate is enforced on the server, so it holds even if the phone is offline when the walk happens.

Verified against

Common questions

What does this lightning protection system annual checklist cover?
4 items across 3 sections, covering inspection observed, grounds and connections, findings and records. Each item spells out what the person walking the job is actually looking for, not just a box to tick.
Who should run this inspection?
The facilities lead documenting the visit while the qualified lightning protection inspector performs the periodic inspection.
When in the schedule should this walk happen?
On the periodic cycle, scheduled with the inspector so the continuity checks and any findings are witnessed and recorded, especially after major roof work.
Why does every item ask for a photo?
6 of the 4 items call for photo evidence. A checklist answer without the photo is a claim; the photo is what makes the record worth something in a dispute and lets a reviewer approve work without re-walking the job.
What most often fails a lightning protection system annual inspection?
Inspector's findings left on the inspection report and never turned into work orders, so the same loose terminal shows up year after year. Down-conductor continuity called good from a visual only, with the inspector's actual continuity check never observed or recorded.
Can I use this checklist in RTI?