Free checklist
PaintingPainting punch checklist
Painting punch is where small misses become callbacks after the crew has demobilized. This checklist walks the finished work the way the owner and the next trade will see it, with the photo that closes each item instead of a note that reopens it. Work is commonly verified against manufacturer data sheets, MPI guidance. Confirm the edition your authority having jurisdiction has adopted.
The checklist
Every item, and the photo evidence it needs
The photo count on each row is what RTI would require before the item can be submitted. Work the list here and watch the gate hold, or load it into RTI and let it enforce the real thing.
Common callbacks
Damage shot as found and assigned before repainting
Every gouge, scuff or mark photographed before touch-up and tagged to paint or to the trade or move-in crew that caused it.
Scuffs washed first, painted only if they stay
Marks from move-in or cleaning crews tried with a mild wash before any touch-up, so sound paint is left alone.
No photoFlashing spots repainted to the nearest break
Where a touch-up shows, the whole wall or panel rolled corner to corner instead of dabbing the spot again.
No photoPeeling or blistered paint traced to a cause
Any lifted coating scraped back and the source (moisture, a leak, poor adhesion) found and fixed before recoating.
No photoOpen joints at casing, crown and base recaulked
Any gaps that opened at trim as the building dried out caulked, tooled and painted to match the trim.
No photo
Repair and proof
Each touch-up blended and photographed in ambient light
The repaired area viewed from standing distance in normal room light, not just under a work light.
Repair located with a wide shot of the wall
A wide photo placing the repair on the wall and in the room, so closure is verifiable remotely.
Signoff
No remaining paint items before room signoff
All punch items in the room closed with photos before the room is marked complete.
Super has the last touch-up date for each cleared room
Rooms with every paint item closed listed with the date of the last touch-up, so furniture and wall hangings wait out the cure time on the can.
No photo
What usually sends this back
The failures are almost always the evidence, not the work
- Touch-up in a different sheen or batch flashing visibly against the original coat.
- Damage photographed so tight nobody can tell which wall or room it belongs to.
Verified against
Common questions
6 answers
- What does this painting punch checklist cover?
- 9 items across 3 sections, covering common callbacks, repair and proof, signoff. Each item spells out what the person walking the job is actually looking for, not just a box to tick.
- Who should run this inspection?
- The painting foreman on a callback, or the GC's superintendent closing finish punch items room by room.
- When in the schedule should this walk happen?
- During closeout, after final cleaning and move-in traffic have had their way with the finished surfaces.
- Why do these items ask for a photo?
- 4 of the 9 items call for photo evidence, 5 photos in all. A checklist answer without the photo is a claim; the photo is what makes the record worth something in a dispute and lets a reviewer approve work without re-walking the job.
- What most often fails a painting punch inspection?
- Touch-up in a different sheen or batch flashing visibly against the original coat. Damage photographed so tight nobody can tell which wall or room it belongs to.
- Can I use this checklist in RTI?
- Yes. Start a free RTI workspace, build this list as a checklist, and the Photo Gate holds the submit button until every mandatory item is answered and its photos are attached. Approved inspections roll into a branded turnover package with a tamper evident audit trail.
Related checklists
Run it with the Photo Gate
A checklist nobody can submit half-finished
Load this list into RTI, stick a QR tag on the area it covers, and the submit button stays locked until every mandatory item is answered and the 5 required photos exist. Approved walks roll into a branded turnover package with a tamper evident record behind every line.
See all 508 checklists · 6741 items and 5984 photo requirements in total.