Pavement markings and striping punch is where small misses become callbacks after the crew has demobilized. This checklist walks the finished work the way the owner and the next trade will see it, with the photo that closes each item instead of a note that reopens it. Work is commonly verified against the applicable accessibility standards and the project specifications. Confirm the edition your authority having jurisdiction has adopted.

Items
3
Photos required
5

Who runs it

The GC's superintendent closing striping punch items with the foreman on a callback.

When in the schedule

During closeout, after the lot has seen daylight and a night to reveal thin or crooked lines and any tracking.

The checklist

Every item, and the photo that proves it

The photo count on each row is what RTI would require before the item can be submitted. Copy the list as is, or load it into RTI and let the gate enforce it.

01

Line repairs

  • Crooked or thin lines re-run

    Lines that are off-line, too thin or short of coverage corrected to full width and alignment, not just touched up.

    2 photos
  • Tracking and overspray cleaned up

    Dragged or tracked material and overspray outside the masked lines removed or ground off.

    1 photo
02

Completeness

  • Missed stalls and markings completed

    Any stall, aisle, symbol or legend skipped in the first pass added and matched to the rest of the lot before signoff.

    2 photos

What usually sends this back

The failures are almost always the evidence, not the work

  • A crooked line painted over rather than removed, so the old shadow shows through the correction.
  • A missed stall or aisle added later in a slightly different width or color that no longer matches the rest of the lot.

Run it with the Photo Gate

A checklist nobody can submit half-finished

Load this list into RTI, stick a QR tag on the area it covers, and the submit button stays locked until every mandatory item is answered and the 5 required photos exist. Approved walks roll into a branded turnover package with a tamper-evident record behind every line.

Submission state

Mandatory items answered3 of 3
Photos attached2 of 5
Submit locked, 3 photos missing

The gate is enforced on the server, so it holds even if the phone is offline when the walk happens.

Common questions

What does this pavement markings and striping punch checklist cover?
3 items across 2 sections, covering line repairs, completeness. Each item spells out what the person walking the job is actually looking for, not just a box to tick.
Who should run this inspection?
The GC's superintendent closing striping punch items with the foreman on a callback.
When in the schedule should this walk happen?
During closeout, after the lot has seen daylight and a night to reveal thin or crooked lines and any tracking.
Why does every item ask for a photo?
5 of the 3 items call for photo evidence. A checklist answer without the photo is a claim; the photo is what makes the record worth something in a dispute and lets a reviewer approve work without re-walking the job.
What most often fails a pavement markings and striping punch inspection?
A crooked line painted over rather than removed, so the old shadow shows through the correction. A missed stall or aisle added later in a slightly different width or color that no longer matches the rest of the lot.
Can I use this checklist in RTI?