Checklists by trade
3 lists · 11 items · 19 photosOperable partitions inspection checklists
Operable partitions inspection checklists for the rough-in, final and punch walks: 3 free lists, 11 items and 19 photo requirements, each item naming what to look for and the photo that proves it.
The operable partitions walks, in build order
Operable partitions Rough-in· Operable partitionsOperable partitions rough-in inspection checklistStructural support for the track above the ceiling verified against the panel weight, track level and straight, and power and pocket coordinated before the ceiling closes4 items8 photosOperable partitions Final· Operable partitionsOperable partitions final inspection checklistFinished partition operates and stacks smoothly, top and bottom seals engage for the rated acoustic performance, and it closes tight at the jambs4 items7 photosOperable partitions Punch· Operable partitionsOperable partitions punch checklistCloseout walk for dragging panels, seal gaps and latch or closure adjustment3 items4 photos
Where each walk sits in the schedule
- Operable partitions rough-in inspection checklistrough-in
- After the overhead track support is framed and the track is hung, and before the ceiling closes — once the grid and tile are in, nothing above the track can be reached or corrected. Run by: The partition installer's field lead with the GC's superintendent, coordinating with the framer and electrician before the ceiling contractor closes in.
- Operable partitions final inspection checklistfinal
- After the ceiling and finishes are complete and the floor is down, before the room is handed over and staff are trained on the wall. Run by: The partition installer's field lead with the GC's superintendent, demonstrating the wall before turnover.
- Operable partitions punch checklistpunch
- During closeout, once the room is fully finished and the wall has been cycled a few times in real use. Run by: The partition installer on a callback, or the GC's superintendent closing partition punch items.
What most often sends operable partitions work back
- Track hung off the ceiling grid or a joist that was never sized for the loaded panel weight, so it sags the first time the wall is stacked.
- Track set level but not straight, so panels bind and drag along part of the run.
- Ceiling closed before the pocket framing and the panel-storage clearance are confirmed, trapping panels that no longer clear the opening.
- Bottom sweep seals set high so the wall glides easily, which quietly gives away the acoustic rating the wall was bought for.
- Panels stack and operate fine empty but bind or won't latch once the room finishes and floor tolerances are real.
- Closure at the jambs adjusted on one end while the far jamb is left with a light gap that leaks sound.
- A dragging panel adjusted at the shoe when the real cause is the track loading down under weight, so the drag comes right back.
- Seal gap chased at the panel while the top seal is the one not deploying fully, so the acoustic complaint stays.
Common questions
- Which operable partitions inspections do these checklists cover?
- Operable partitions rough-in inspection checklist (rough-in): After the overhead track support is framed and the track is hung, and before the ceiling closes — once the grid and tile are in, nothing above the track can be reached or corrected. Operable partitions final inspection checklist (final): After the ceiling and finishes are complete and the floor is down, before the room is handed over and staff are trained on the wall. Operable partitions punch checklist (punch): During closeout, once the room is fully finished and the wall has been cycled a few times in real use.
- Who runs an operable partitions inspection?
- The partition installer's field lead with the GC's superintendent, coordinating with the framer and electrician before the ceiling contractor closes in. The partition installer's field lead with the GC's superintendent, demonstrating the wall before turnover. The partition installer on a callback, or the GC's superintendent closing partition punch items.
- What most often sends operable partitions work back?
- Track hung off the ceiling grid or a joist that was never sized for the loaded panel weight, so it sags the first time the wall is stacked. Track set level but not straight, so panels bind and drag along part of the run. Ceiling closed before the pocket framing and the panel-storage clearance are confirmed, trapping panels that no longer clear the opening. Bottom sweep seals set high so the wall glides easily, which quietly gives away the acoustic rating the wall was bought for.
- Can I run these checklists in RTI?
- Yes. Start a free RTI workspace and load any of the 3 lists (11 items in total). The Photo Gate holds the submit button until every mandatory item is answered and its photos are attached, and approved inspections roll into a branded turnover package with a tamper-evident audit trail.