Field directive
Also called: field order, field instruction
A field directive is a written order given on the job — often by the owner's rep, architect or engineer — telling the contractor to proceed with something before it's been captured in a change order or a fully priced directive. It keeps the field moving on minor changes and urgent conditions. Its value, and its risk, is that it authorizes action ahead of the contract mechanism, so it must be written and logged, not spoken and forgotten.
Why it matters
Work performed on a directive still has to be paid for and, if it adds scope, reconciled into a change order. A directive captured only as a verbal instruction is where scope creep and unpaid extra work begin. Written and logged, it's the trail that connects a field decision to its eventual cost and to any as-built change it caused.
How it shows up on site
A field directive that carries cost or time impact should flow into a construction change directive or change order rather than dying in a superintendent's notebook. Documenting the directed work — including a photo of the condition that prompted it — is what supports the reconciliation later.
Related terms
- Change orderA signed amendment to the contract that changes the scope, price or schedule, agreed by owner and contractor before the changed work proceeds.
- Construction change directive (CCD)An owner-signed order directing the contractor to proceed with a change before the price or time impact has been fully agreed.
- Request for information (RFI)A formal written question from the contractor to the design team when the drawings or specs are unclear, conflicting or incomplete.
- Daily construction reportThe dated record of what happened on site each day — crews present, work done, weather, deliveries, inspections and issues.
- Punch listThe running list of incomplete or defective work a contractor has to fix before an area is accepted and closed out.
- Nonconformance report (NCR)A formal record raised when installed work does not meet the drawings, specs or an accepted standard, and the plan to resolve it.