Field directive

Also called: field order, field instruction

A field directive is a written order given on the job — often by the owner's rep, architect or engineer — telling the contractor to proceed with something before it's been captured in a change order or a fully priced directive. It keeps the field moving on minor changes and urgent conditions. Its value, and its risk, is that it authorizes action ahead of the contract mechanism, so it must be written and logged, not spoken and forgotten.

Why it matters

Work performed on a directive still has to be paid for and, if it adds scope, reconciled into a change order. A directive captured only as a verbal instruction is where scope creep and unpaid extra work begin. Written and logged, it's the trail that connects a field decision to its eventual cost and to any as-built change it caused.

How it shows up on site

A field directive that carries cost or time impact should flow into a construction change directive or change order rather than dying in a superintendent's notebook. Documenting the directed work — including a photo of the condition that prompted it — is what supports the reconciliation later.

Knowing the term is step one. Proving it is the job.

RTI holds the submit button until every mandatory item is answered and the photos are attached, then chains the record so it can be proven untouched later.