How to inspect sitework and earthwork
Sitework sets the stage for everything else, and most of it ends up underground where nobody can check it again. The inspection follows the earth: erosion control before you dig, the excavation and its safety, the subgrade before fill, each lift of fill and its compaction, the utilities in the trench, and the final grades. Miss a layer and you're excavating to prove it.
For the superintendent and QC manager verifying earthwork and underground utilities against the civil drawings, geotechnical report, and the testing lab's results.
Step by step
Verify erosion and sediment control first
Before ground is broken, confirm silt fence, inlet protection, construction entrances, and any required controls are installed per the SWPPP. This is both a permit condition and the first thing an inspector looks for.
Check excavation, benching, and trench safety
Confirm excavation reaches the right lines and grades, that slopes, benching, or shoring meet the safety requirements for the soil and depth, and that spoil is set back from the edge. Trench safety is life-safety scope — verify the protective system is in place before anyone enters.
Confirm the subgrade and proof-roll
Verify the subgrade is at grade, free of organics and soft spots, and proof-rolled where required, with the geotechnical engineer approving it where their sign-off governs. Soft subgrade under a slab or pavement pumps and fails.
Inspect fill placement and compaction testing
Confirm the fill material matches the spec, that it's placed in the specified lift thickness at proper moisture, and that the testing lab takes density tests at the required frequency and they pass. Fill placed too thick or too dry never reaches density.
Verify underground utilities before backfill
Check line, grade, slope, bedding, and material for storm, sanitary, water, and conduit, and confirm required pressure or leak testing is done before the trench is closed. Bedding and haunching support the pipe — skip it and the pipe deflects.
Confirm base course and aggregate
Under pavements and slabs, verify aggregate base type, thickness, and compaction, and that it's shaped to the right grade and cross-slope. The base does the structural work under the wearing surface.
Check final grades, drainage, and stabilization
Verify finish grades drain away from the building and to the drainage structures per the plan, that positive slope is maintained, and that disturbed areas are stabilized. Standing water against the building is a grading defect, not a landscaping one.
Document each layer before it's covered
Photograph the subgrade, utility trenches, and compacted lifts before they're buried, keep the density and utility test reports with the record, and log any failing test or out-of-grade condition as a nonconformance.
What gets missed
- Backfilling a utility trench before line, grade, and required pressure or leak testing are verified.
- Placing fill in lifts too thick or too dry to ever reach the specified density.
- Founding a slab or pavement on soft, unproof-rolled subgrade full of organics.
- Letting erosion control lapse, which turns a rain event into a permit violation and a mud problem.
- Final grades that pond water against the building instead of draining to the structures.
Questions people ask
- Why does earthwork need so much testing?
- Because compaction can't be judged by eye, and everything you build sits on it. Density tests at each lift are the proof that the fill will carry load without settling — and once it's buried, that report is the only record you have.
- Who approves the subgrade and bearing?
- Your QC confirms line and grade, the testing lab runs the density and proof-roll, and the geotechnical engineer approves bearing where their sign-off is required. Record all of it; the layers get covered fast.
Terms worth knowing
Checklists that make this a one-tap job
Free, field-ready checklists, each with the photo every item needs before it can be submitted.
Related guides
- How to inspect foundationsInspect foundations from bearing to backfill — soil, formwork, reinforcement, waterproofing, and anchor bolts — with the pre-pour hold point that governs it.
- How to inspect a concrete pourRun the pre-pour inspection, watch the pour, and check the finish — formwork, rebar, embeds, mix, and curing — because concrete only gets inspected once.
- How to set hold points and witness pointsDecide which steps in an ITP are hard stops and which are invitations to observe, name who releases each, and set the notice periods that make them stick.
Reading the steps is one thing. Proving you walked them is the job.
RTI holds the submit button until every mandatory item is answered and the photos are attached, then chains the record so it can be proven untouched later.