SiteworkSitework final inspection checklist
Sitework final inspection is where the punch list is either short or expensive. This checklist walks the finished work the way an owner or AHJ will see it: devices on, systems running, everything labeled. Each item gets the photo that closes it instead of reopening it. Work is commonly verified against the project geotechnical report, the applicable building code. Confirm the edition your authority having jurisdiction has adopted.
The checklist
Every item, and the photo evidence it needs
The photo count on each row is what RTI would require before the item can be submitted. Work the list here and watch the gate hold, or load it into RTI and let it enforce the real thing.
Drainage
Site drains away from structures everywhere
Positive slope at every building perimeter, no birdbaths at foundations, scuppers and area drains unobstructed.
Pavement and flatwork free of ponding after a rain
The site walked wet, any standing water located and photographed for correction.
Inlets, sumps and outfalls cleaned of construction sediment
Grates open, catch basin sumps and pipe ends cleared of silt, outfalls stabilized with no scour at the discharge point.
Stormwater ponds and swales finished to the drawing elevations
Where the site has detention, swales or treatment areas, bottom and outlet elevations checked against the drawings and construction sediment removed.
No photoTemporary erosion controls removed only behind stabilization
Silt fence, inlet protection and the construction entrance taken out only where permanent cover is established, per the erosion control plan and permit.
Flatwork condition
Flatwork free of cracking, scaling and trip edges
Joints tooled and sealed where specified, no vertical displacement at joints on accessible routes.
Curb, gutter and pavement markings complete
Curb lines straight and undamaged, striping and signage per the site plan.
Curb ramps finished with detectable warnings and flush edges
Where the site has curb ramps, warning panels cover the full ramp width and are bonded tight, and the ramp meets the gutter or street without a lip.
No photo
Paving and restoration
Lids, grates and boxes flush with the finished paving
Manhole lids, valve boxes, cleanouts and grates in pavement and walks sitting flush, with no trip lip and no lid rocking under foot.
Pavement and walk edges backfilled and supported
Shoulders and back of curb backfilled and compacted up to the edge, no exposed base or undercut edge where the pavement could break off.
Staging, haul routes and disturbed areas restored
Ground disturbed outside the grading limits, including laydown areas and haul routes, regraded and restored to the condition the contract documents call for.
Street, sidewalk and neighbor tie-ins free of equipment damage
Public walks, street edges and adjoining property at the tie-ins checked for cracking, rutting or settlement, with any damage photographed for repair.
Records
Compaction and pre-pour records on file for every area
The photo record export shows test results and pour releases for each utility run and pour section.
As-built survey of grades, inverts and rims compiled
Finish grades, utility inverts and structure rim elevations surveyed and matched to the field record, ready for the engineer of record's review.
No photoMunicipal and utility inspection outcomes logged
Dates and results of the city, utility and permit inspections on water, sewer, storm and right-of-way work recorded, with open comments listed.
No photo
What usually sends this back
The failures are almost always the evidence, not the work
- Ponding discovered at the first storm after turnover because the site was never walked in wet weather.
- Finish grades against the building sloped toward the foundation where landscaping changed the drainage path.
Common questions
6 answers
- What does this sitework final checklist cover?
- 15 items across 4 sections, covering drainage, flatwork condition, paving and restoration, records. Each item spells out what the person walking the job is actually looking for, not just a box to tick.
- Who should run this inspection?
- The GC's superintendent walking the site after paving and flatwork, before landscaping covers the drainage patterns.
- When in the schedule should this walk happen?
- After paving, flatwork and final grading are complete, ideally verified during or right after a rain event.
- Why do these items ask for a photo?
- 11 of the 15 items call for photo evidence, 14 photos in all. A checklist answer without the photo is a claim; the photo is what makes the record worth something in a dispute and lets a reviewer approve work without re-walking the job.
- What most often fails a sitework final inspection?
- Ponding discovered at the first storm after turnover because the site was never walked in wet weather. Finish grades against the building sloped toward the foundation where landscaping changed the drainage path.
- Can I use this checklist in RTI?
- Yes. Start a free RTI workspace, build this list as a checklist, and the Photo Gate holds the submit button until every mandatory item is answered and its photos are attached. Approved inspections roll into a branded turnover package with a tamper evident audit trail.
Related checklists
Run it with the Photo Gate
A checklist nobody can submit half-finished
Load this list into RTI, stick a QR tag on the area it covers, and the submit button stays locked until every mandatory item is answered and the 14 required photos exist. Approved walks roll into a branded turnover package with a tamper evident record behind every line.
See all 508 checklists · 6741 items and 5984 photo requirements in total.