Water treatment chemical feed system annual maintenance checklist
The annual chemical feed system service is the deep pass: the measurements, cleanings and tests a quarterly round doesn't reach. This checklist keeps the full service on record with the photos that make it defensible later. Work is commonly verified against manufacturer's published instructions. Confirm the edition your authority having jurisdiction has adopted.
- Items
- 6
- Photos required
- 9
- Built for
- Subcontractors
Who runs it
The water treatment service contractor on the annual service, when the loop can be sampled and the controller taken through its ranges.
When in the schedule
Once a year, timed with the closed-loop and condenser-water annual so probe drift and pump output get corrected against a real sample.
The checklist
Every item, and the photo that proves it
The photo count on each row is what RTI would require before the item can be submitted. Copy the list as is, or load it into RTI and let the gate enforce it.
Pump calibration
- 2 photos
Metering pump output verified by draw-down
Pump timed against a calibration column or measured draw-down, actual output compared to the setting and corrected, not read off the dial.
- 1 photo
Diaphragm and valves inspected
Pump head opened where due, diaphragm and suction/discharge valves inspected for swelling or crystallization, seals replaced per the service kit.
Controller and probes
- 2 photos
Probe cleaned and checked against reference
Conductivity or ORP probe pulled, cleaned of scale and film, then checked against a known reference solution and calibrated to it.
- 1 photo
Setpoints and alarms exercised
Controller taken through its dosing and bleed setpoints, low-level and no-flow alarms confirmed to interrupt feed as intended.
Injection and delivery
- 2 photos
Injection quill pulled and cleared
Quill removed from the line, scale and crystallization cleared, check valve reseating cleanly, quill reinstalled to the correct depth in the flow.
- 1 photo
Tubing runs replaced where degraded
Suction and discharge tubing checked end to end for hardening and cracking, sections replaced where degraded, containment cleaned out.
What usually sends this back
The failures are almost always the evidence, not the work
- Metering pump output taken from the dial setting and never checked against a draw-down, so the loop is over- or under-dosed all year.
- Conductivity probe cleaned but never checked against a reference solution, so the controller doses to a drifted number.
- Injection quill left in place until it snaps off in the flow because scale was never cleared from it on a service.
Run it with the Photo Gate
A checklist nobody can submit half-finished
Load this list into RTI, stick a QR tag on the area it covers, and the submit button stays locked until every mandatory item is answered and the 9 required photos exist. Approved walks roll into a branded turnover package with a tamper-evident record behind every line.
Submission state
The gate is enforced on the server, so it holds even if the phone is offline when the walk happens.
Common questions
- What does this water treatment chemical feed system annual checklist cover?
- 6 items across 3 sections, covering pump calibration, controller and probes, injection and delivery. Each item spells out what the person walking the job is actually looking for, not just a box to tick.
- Who should run this inspection?
- The water treatment service contractor on the annual service, when the loop can be sampled and the controller taken through its ranges.
- When in the schedule should this walk happen?
- Once a year, timed with the closed-loop and condenser-water annual so probe drift and pump output get corrected against a real sample.
- Why does every item ask for a photo?
- 9 of the 6 items call for photo evidence. A checklist answer without the photo is a claim; the photo is what makes the record worth something in a dispute and lets a reviewer approve work without re-walking the job.
- What most often fails a water treatment chemical feed system annual inspection?
- Metering pump output taken from the dial setting and never checked against a draw-down, so the loop is over- or under-dosed all year. Conductivity probe cleaned but never checked against a reference solution, so the controller doses to a drifted number. Injection quill left in place until it snaps off in the flow because scale was never cleared from it on a service.