Metal wall panels rough-in is the last time the work is fully visible. Once the cover inspection passes and the walls, ceilings and slabs close, every defect left behind becomes a demolition bill. This checklist walks the rough-in in the order the work goes in, with the photo each item needs before it gets buried. Work is commonly verified against manufacturer's published instructions, the applicable building code. Confirm the edition your authority having jurisdiction has adopted.

Items
4
Photos required
8

Who runs it

The panel foreman checking each elevation ahead of the setting crew, or the GC's superintendent releasing walls before panels go up.

When in the schedule

After girts or subgirts, the water-resistive barrier and flashing are in, before panels start — once the wall is covered, a barrier lap or a missed flashing can't be seen or fixed.

The checklist

Every item, and the photo that proves it

The photo count on each row is what RTI would require before the item can be submitted. Copy the list as is, or load it into RTI and let the gate enforce it.

01

Substrate and framing

  • Girts or subgirts straight, plumb and in plane

    Girt and subgirt lines checked with a string or level across the elevation, plane consistent so panels lie flat, shims added where the line is out.

    2 photos
02

Weather barrier and flashing

  • Water-resistive barrier continuous and correctly lapped

    Barrier continuous over the substrate, laps shingled to shed water downward, seams and penetrations sealed per the manufacturer.

    2 photos
  • Flashing and counterflashing installed at transitions

    Head, sill, jamb and transition flashing in place with end dams and correct laps, integrated with the barrier to drain to the exterior face.

    2 photos
03

Clips and fasteners

  • Clip layout and fasteners match the approved pattern

    Clip spacing and fastener type per the approved layout, fasteners into the framing and set to the right tension, no missed or spun fasteners along the line.

    2 photos

What usually sends this back

The failures are almost always the evidence, not the work

  • Water-resistive barrier lapped the wrong way at a horizontal joint, shingling water behind the barrier instead of over it.
  • Counterflashing and end dams skipped at a head or a transition because the panel delivery was already staged.
  • Clips fastened to a bowed or out-of-plane girt line, so the finished panels telegraph the waviness and oil-can along the run.

Run it with the Photo Gate

A checklist nobody can submit half-finished

Load this list into RTI, stick a QR tag on the area it covers, and the submit button stays locked until every mandatory item is answered and the 8 required photos exist. Approved walks roll into a branded turnover package with a tamper-evident record behind every line.

Submission state

Mandatory items answered4 of 4
Photos attached5 of 8
Submit locked, 3 photos missing

The gate is enforced on the server, so it holds even if the phone is offline when the walk happens.

Common questions

What does this metal wall panels rough-in checklist cover?
4 items across 3 sections, covering substrate and framing, weather barrier and flashing, clips and fasteners. Each item spells out what the person walking the job is actually looking for, not just a box to tick.
Who should run this inspection?
The panel foreman checking each elevation ahead of the setting crew, or the GC's superintendent releasing walls before panels go up.
When in the schedule should this walk happen?
After girts or subgirts, the water-resistive barrier and flashing are in, before panels start — once the wall is covered, a barrier lap or a missed flashing can't be seen or fixed.
Why does every item ask for a photo?
8 of the 4 items call for photo evidence. A checklist answer without the photo is a claim; the photo is what makes the record worth something in a dispute and lets a reviewer approve work without re-walking the job.
What most often fails a metal wall panels rough-in inspection?
Water-resistive barrier lapped the wrong way at a horizontal joint, shingling water behind the barrier instead of over it. Counterflashing and end dams skipped at a head or a transition because the panel delivery was already staged. Clips fastened to a bowed or out-of-plane girt line, so the finished panels telegraph the waviness and oil-can along the run.
Can I use this checklist in RTI?
Yes. Start a free RTI workspace, build this list as a checklist, and the Photo Gate holds the submit button until every mandatory item is answered and its photos are attached. Approved inspections roll into a branded turnover package with a tamper-evident audit trail.