Cold-formed metal framing

Cold-formed metal framing final inspection checklist

Cold-formed metal framing final inspection is where the punch list is either short or expensive. This checklist walks the finished work the way an owner or AHJ will see it: devices on, systems running, everything labeled. Each item gets the photo that closes it instead of reopening it. Work is commonly verified against AISI cold-formed steel standards, the applicable building code. Confirm the edition your authority having jurisdiction has adopted.

The checklist

Every item, and the photo evidence it needs

The photo count on each row is what RTI would require before the item can be submitted. Work the list here and watch the gate hold, or load it into RTI and let it enforce the real thing.

01

Alignment

  • Walls plumb, straight and in plane

    Plumb checked at ends and mid-height, wall face straight along its length with no bow, adjacent walls in the same plane at intersections.

  • Ceilings and soffits level and to layout

    Framed ceilings and soffits level to the line, hangers and framing tight, dimensions matching the reflected ceiling plan.

  • Wall heights reach the line each wall type calls for

    Walls scheduled to deck run to the deck, and walls that stop above the ceiling reach the height on the wall type, checked room by room rather than on one wall.

  • Critical room dimensions measured stud face to stud face

    Corridor widths, toilet room clearances and casework or appliance runs measured to the framing, allowing for board layers, against the dimensioned plans.

  • Walls stiff when pushed at mid-height and at free ends

    Tall walls, wall ends and walls that stop short of structure pushed by hand for movement or rattle; loose heads, missing bracing or unfastened ends reported.

    No photo
02

Openings and connections

  • Openings framed to the correct rough size and reinforced

    Rough opening dimensions confirmed against door and window schedules, jambs and headers complete, reinforcing at openings in place.

  • All connections complete and tight

    Stud-to-track, bridging and structural connections fully fastened with nothing left loose at corners, intersections or crew hand-off lines.

  • Bottom track bearing on the floor along its full length

    Track sighted along each wall for spans bridging a dip in the slab or lifting at a hump; gaps shimmed or grouted as the submittal allows so studs don't hang off the anchors.

  • Recessed cabinet and panel openings framed at their locations

    Openings for extinguisher cabinets, electrical panels and access panels framed with head and sill track at the sizes and heights the drawings show, not cut in later.

    No photo
03

Records and handoff

  • Field changes to the approved submittal documented

    Any stud substitution, spacing change or moved opening written up and sent to the architect and delegated engineer for review, and marked on the as-built set.

    No photo
  • Delegated engineer's field observation report on file

    Where the CFMF design is delegated, the design engineer's site observation letter or report for the area is in the project file, with open items listed.

    No photo
  • Walls on hold marked so the board crew skips them

    Walls still waiting on an inspection or a framing correction tagged at the wall and listed for the board foreman, so no face is closed early.

    No photo
  • Open framing items assigned to the framing foreman

    Each open item from this walk given to the framing foreman with its wall or room on the plan and a date to close it, before the punch walk.

    No photo

What usually sends this back

The failures are almost always the evidence, not the work

  • A wall plumb at the ends but bowed in the middle, so the finished face waves once board is hung.
  • Corner and intersection connections left loose where two crews met and each assumed the other tied them.
  • A framed opening left the wrong rough size, forcing the door or window trade to shim or refit later.

Common questions

6 answers

What does this cold-formed metal framing final checklist cover?
13 items across 3 sections, covering alignment, openings and connections, records and handoff. Each item spells out what the person walking the job is actually looking for, not just a box to tick.
Who should run this inspection?
The GC's superintendent with the framing foreman, walking finished walls before the next trade takes over.
When in the schedule should this walk happen?
After framing is complete on an area and before board, cladding or ceiling grid starts, so alignment problems don't get built into the finishes.
Why do these items ask for a photo?
7 of the 13 items call for photo evidence, 10 photos in all. A checklist answer without the photo is a claim; the photo is what makes the record worth something in a dispute and lets a reviewer approve work without re-walking the job.
What most often fails a cold-formed metal framing final inspection?
A wall plumb at the ends but bowed in the middle, so the finished face waves once board is hung. Corner and intersection connections left loose where two crews met and each assumed the other tied them. A framed opening left the wrong rough size, forcing the door or window trade to shim or refit later.