Sitework pre-pour inspection checklist
A sitework pre-pour inspection is the last look at everything the concrete is about to bury — reinforcement, embeds, sleeves, vapor barrier. Once the truck arrives there is no recheck, so this checklist walks the placement in pour order with the photo each item needs before the pour starts. Work is commonly verified against the project geotechnical report, the applicable building code — confirm the edition your authority having jurisdiction has adopted.
- Items
- 6
- Photos required
- 13
- Built for
- General contractors
Who runs it
The GC's superintendent with the flatwork foreman, releasing each pour area for concrete.
When in the schedule
After base, forms, reinforcement and embeds are complete on a pour area, the day the trucks are scheduled.
The checklist
Every item, and the photo that proves it
The photo count on each row is what RTI would require before the item can be submitted. Copy the list as-is, or load it into RTI and let the gate enforce it.
Base and forms
- 2 photos
Base compacted, trimmed and at the correct elevation
Base density test passed for the pour area, surface trimmed to tolerance, no soft or saturated spots.
- 2 photos
Forms straight, braced and at the right line and grade
Form line checked against the layout, stakes and braces solid, top-of-form elevations shot.
Reinforcement and embeds
- 2 photos
Reinforcement size, spacing and chair height per the drawing
Bar or mesh supported at the specified depth, laps tied, no reinforcement resting on the base.
- 2 photos
Sleeves, embeds and blockouts set against the layout
Each penetration and embed located from control lines, photographed with the layout reference visible.
- 2 photos
Vapor barrier lapped, sealed and undamaged where specified
Seams lapped and taped, penetrations sealed, no punctures from the reinforcement work.
Release
- 3 photos
Pour area walked end to end and released
One wide photo per pour section showing base, forms and reinforcement in place, tagged to the pour release.
What usually sends this back
The failures are almost always the evidence, not the work
- Base saturated or rutted overnight and poured anyway because the truck was already booked.
- Reinforcement chaired on the subgrade instead of at the correct depth in the slab.
- Sleeves and embeds set from memory instead of against the layout drawing.
Run it with the Photo Gate
A checklist nobody can submit half-finished
Load this list into RTI, stick a QR tag on the area it covers, and the submit button stays locked until every mandatory item is answered and the 13 required photos exist. Approved walks roll into a branded turnover package with a tamper-evident record behind every line.
Submission state
The gate is enforced on the server, so it holds even if the phone is offline when the walk happens.
Common questions
- What does this sitework pre-pour checklist cover?
- 6 items across 3 sections — base and forms, reinforcement and embeds, release. Each item spells out what the person walking the job is actually looking for, not just a box to tick.
- Who should run this inspection?
- The GC's superintendent with the flatwork foreman, releasing each pour area for concrete.
- When in the schedule should this walk happen?
- After base, forms, reinforcement and embeds are complete on a pour area, the day the trucks are scheduled.
- Why does every item ask for a photo?
- 13 of the 6 items call for photo evidence. A checklist answer without the photo is a claim; the photo is what makes the record worth something in a dispute and lets a reviewer approve work without re-walking the job.
- What most often fails a sitework pre-pour inspection?
- Base saturated or rutted overnight and poured anyway because the truck was already booked. Reinforcement chaired on the subgrade instead of at the correct depth in the slab. Sleeves and embeds set from memory instead of against the layout drawing.
- Can I use this checklist in RTI?
- Yes. Start a free RTI workspace, build this list as a checklist, and the Photo Gate holds the submit button until every mandatory item is answered and its photos are attached. Approved inspections roll into a branded turnover package with a tamper-evident audit trail.
Related checklists
See all 101 checklists — 775 items and 1296 photo requirements in total.