A eifs (exterior insulation and finish) pre-cover inspection is the hold point before concealed work disappears behind the next layer. This checklist is built for that walk: verify, photograph, then release the cover, not the other way around. Work is commonly verified against manufacturer's published instructions, the applicable building code. Confirm the edition your authority having jurisdiction has adopted.

The checklist

Every item, and the photo evidence it needs

The photo count on each row is what RTI would require before the item can be submitted. Work the list here and watch the gate hold, or load it into RTI and let it enforce the real thing.

01

Insulation board

  • Board attached and joints as the system requires

    Board set tight with staggered joints and full attachment, no open gaps packed with base coat, rasped flat before coating.

  • Edges back-wrapped at openings and terminations

    Mesh wrapped around board edges at openings and terminations, no raw foam left exposed at any edge.

  • Board label matches the approved submittal

    Board stamp or bundle label photographed showing type and thickness, matched to the insulation the approved system submittal names.

  • Attachment checked on a pulled board

    A freshly set board pulled on each elevation to see adhesive contact or fastener pattern matches the manufacturer's detail, ribbons vertical where the system drains.

  • Board joints kept off the corners of openings

    No board joint lines up with a window or door corner; L-shaped pieces cut around the corners so cracks don't start there.

02

Base coat and mesh

  • Reinforcing mesh fully embedded in the base coat

    Mesh troweled into wet base coat so the pattern is barely visible, laps as specified, not floated on the surface.

  • Aesthetic reveals coated and wrapped

    Reveal grooves lined with mesh and base coat, edges crisp, no bare foam left in the groove.

  • Base coat and mesh labels match the approved submittal

    Base coat pail and mesh roll labels photographed and matched to the approved system, including the mesh weight shown for each zone.

  • Base coat thickness within the manufacturer's range

    Thickness checked at a cut edge or with a gauge against the manufacturer's listed range, no thin spots where the mesh shows through.

  • Diagonal mesh at every opening corner

    Diagonal mesh pieces embedded at each corner of windows, doors and louvers, placed with the field mesh as the manufacturer details.

  • Base coat protected from weather until cured

    Temperatures kept within the manufacturer's application range and rain kept off until cure; tarps or heat noted in the daily log on cold or wet days.

    No photo
03

Joints, openings and release

  • Sealant gap left at openings and penetrations

    Board edge held back from frames and penetrations by the joint width the details show, wrapped edges clean and not filled with base coat.

  • Expansion joints open full depth with edges wrapped

    Board separated at each joint location, both edges back-wrapped, no base coat or mesh bridging the gap.

  • Base coat surface dressed and clean before finish

    Trowel ridges, mesh laps and base coat splatter knocked down flat, surface clean and dry, and primer on where the manufacturer requires before finish starts.

    No photo

What usually sends this back

The failures are almost always the evidence, not the work

  • Reinforcing mesh laid on the wall and skimmed over on top, sitting on the surface instead of embedded in the base coat.
  • Board edges at openings not back-wrapped, leaving raw insulation exposed at a reveal or terminus.
  • Aesthetic reveals cut after the base coat and left with bare foam in the groove instead of a wrapped, coated edge.

Common questions

6 answers

What does this eifs (exterior insulation and finish) pre-cover checklist cover?
14 items across 3 sections, covering insulation board, base coat and mesh, joints, openings and release. Each item spells out what the person walking the job is actually looking for, not just a box to tick.
Who should run this inspection?
The EIFS foreman walking behind the base-coat crew, or the GC's superintendent releasing each elevation for finish.
When in the schedule should this walk happen?
After insulation board, base coat and mesh are on and edges are back-wrapped, before the finish coat goes over it all.
Why do these items ask for a photo?
12 of the 14 items call for photo evidence, 15 photos in all. A checklist answer without the photo is a claim; the photo is what makes the record worth something in a dispute and lets a reviewer approve work without re-walking the job.
What most often fails an eifs (exterior insulation and finish) pre-cover inspection?
Reinforcing mesh laid on the wall and skimmed over on top, sitting on the surface instead of embedded in the base coat. Board edges at openings not back-wrapped, leaving raw insulation exposed at a reveal or terminus. Aesthetic reveals cut after the base coat and left with bare foam in the groove instead of a wrapped, coated edge.