EIFS (exterior insulation and finish) punch is where small misses become callbacks after the crew has demobilized. This checklist walks the finished work the way the owner and the next trade will see it, with the photo that closes each item instead of a note that reopens it. Work is commonly verified against manufacturer's published instructions, the applicable building code. Confirm the edition your authority having jurisdiction has adopted.

The checklist

Every item, and the photo evidence it needs

The photo count on each row is what RTI would require before the item can be submitted. Work the list here and watch the gate hold, or load it into RTI and let it enforce the real thing.

01

Defects

  • Cracks and delamination located and photographed

    Each crack or hollow-sounding area marked and shot close plus a wide shot locating it on the elevation.

  • Repairs cut back to sound material

    Repair opened to sound base coat and board, rebuilt through the full system, not skimmed over at the finish only.

  • Base, doors and lift paths checked for impact damage

    Dents, gouges and punctures at the base, at doors and where lifts worked found and marked; any break that reaches the foam listed for a full-system repair.

  • Repairs feathered to a natural break line

    Patch finish carried to a corner, joint or reveal so the repair doesn't read as a square on the wall in raking light.

    No photo
  • Sills and ledges checked for ponding and staining

    Top surfaces of sills, bands and trim sloped to shed water, with no ponding, dirt streaks or growth below them.

    No photo
02

Later penetrations and repair materials

  • Elevations walked for penetrations added since final

    Each elevation checked for holes cut after the EIFS final for conduit, cameras, signs or piping; any found sealed, with the lamina patched around them.

    No photo
  • Repair materials drawn from the original system and batch

    Repair base coat, mesh and finish from the same manufacturer's system, with finish from the batch recorded for that elevation.

    No photo
03

Sealant and signoff

  • Missed or failed sealant made continuous

    Sealant at terminations and penetrations continuous and tooled, gaps and skips filled against base coat, primed where the EIFS manufacturer requires, not finish coat.

  • No remaining EIFS items before area release

    All punch items on the elevation closed with photos before the area is released to turnover.

What usually sends this back

The failures are almost always the evidence, not the work

  • A hairline crack chased with finish coat at the surface while the base coat behind it is still cracked.
  • A hollow-sounding area tapped and noted but closed out without opening it to find why the base coat let go.

Common questions

6 answers

What does this eifs (exterior insulation and finish) punch checklist cover?
9 items across 3 sections, covering defects, later penetrations and repair materials, sealant and signoff. Each item spells out what the person walking the job is actually looking for, not just a box to tick.
Who should run this inspection?
The EIFS foreman on a callback, or the GC's superintendent closing envelope punch items.
When in the schedule should this walk happen?
During closeout, after other trades have worked against the wall and the first weather has revealed sealant misses.
Why do these items ask for a photo?
5 of the 9 items call for photo evidence, 7 photos in all. A checklist answer without the photo is a claim; the photo is what makes the record worth something in a dispute and lets a reviewer approve work without re-walking the job.
What most often fails an eifs (exterior insulation and finish) punch inspection?
A hairline crack chased with finish coat at the surface while the base coat behind it is still cracked. A hollow-sounding area tapped and noted but closed out without opening it to find why the base coat let go.
Can I use this checklist in RTI?
Yes. Start a free RTI workspace, build this list as a checklist, and the Photo Gate holds the submit button until every mandatory item is answered and its photos are attached. Approved inspections roll into a branded turnover package with a tamper evident audit trail.