Skip to content
RTI

Free checklist

Precast concrete

Precast concrete rough-in inspection checklist

Precast concrete rough-in is the last time the work is fully visible. Once the cover inspection passes and the walls, ceilings and slabs close, every defect left behind becomes a demolition bill. This checklist walks the rough-in in the order the work goes in, with the photo each item needs before it gets buried. Work is commonly verified against PCI guidance, the applicable building code. Confirm the edition your authority having jurisdiction has adopted.

Items
7
Photos required
11

Who runs it

The GC's superintendent walking the raise with the erector's foreman, releasing each bay before the crane moves on.

When in the schedule

During erection, piece by piece as panels and members are landed, before any topping is poured or the connection is closed in.

The checklist

Every item, and the photo that proves it

The photo count on each row is what RTI would require before the item can be submitted. Copy the list as is, or load it into RTI and let the gate enforce it.

01

Bearing and alignment

  • Bearing pads seated and members at correct elevation

    Pad centered and fully under the bearing, member elevation and line checked against the erection drawing before release.

    2 photos
  • Leveling shims placed and stable

    Shim stacks solid, non-tipping and within the detailed height, no makeshift shims substituted in the field.

    1 photo
02

Connections

  • Connection hardware matches the erection detail

    Plates, angles, bolts and weld sizes match the piece connection detail, bolts torqued or welds sized as shown.

    2 photos
  • Field welds complete, not just tack-held

    Every connection weld run out to the detailed size, no piece left carried on erection tacks alone.

    2 photos
  • Embeds and dowels engaged as shown

    Cast-in embeds and projecting dowels line up and engage the mating piece per the detail, none cut or bent to fit.

    1 photo
03

Grout and bracing

  • Grout placed at bearings and keyways

    Bearing joints and shear keyways fully packed with the specified grout, consolidated with no voids before closure.

    2 photos
  • Temporary bracing in place until connections are made

    Erection bracing installed and left engaged until the permanent connections and grout have taken the load.

    1 photo

What usually sends this back

The failures are almost always the evidence, not the work

  • Bearing pads shifted or pinched during setting, leaving the member bearing on the edge instead of the full pad.
  • Field welds tacked to hold the piece for the crane and never completed to the full connection detail.
  • Grout skipped at a keyway or bearing because the next piece was already swinging in, then buried under topping.

Run it with the Photo Gate

A checklist nobody can submit half-finished

Load this list into RTI, stick a QR tag on the area it covers, and the submit button stays locked until every mandatory item is answered and the 11 required photos exist. Approved walks roll into a branded turnover package with a tamper-evident record behind every line.

Submission state

Mandatory items answered7 of 7
Photos attached8 of 11
Submit locked, 3 photos missing

The gate is enforced on the server, so it holds even if the phone is offline when the walk happens.

Verified against

Common questions

What does this precast concrete rough-in checklist cover?
7 items across 3 sections, covering bearing and alignment, connections, grout and bracing. Each item spells out what the person walking the job is actually looking for, not just a box to tick.
Who should run this inspection?
The GC's superintendent walking the raise with the erector's foreman, releasing each bay before the crane moves on.
When in the schedule should this walk happen?
During erection, piece by piece as panels and members are landed, before any topping is poured or the connection is closed in.
Why does every item ask for a photo?
11 of the 7 items call for photo evidence. A checklist answer without the photo is a claim; the photo is what makes the record worth something in a dispute and lets a reviewer approve work without re-walking the job.
What most often fails a precast concrete rough-in inspection?
Bearing pads shifted or pinched during setting, leaving the member bearing on the edge instead of the full pad. Field welds tacked to hold the piece for the crane and never completed to the full connection detail. Grout skipped at a keyway or bearing because the next piece was already swinging in, then buried under topping.
Can I use this checklist in RTI?
Yes. Start a free RTI workspace, build this list as a checklist, and the Photo Gate holds the submit button until every mandatory item is answered and its photos are attached. Approved inspections roll into a branded turnover package with a tamper-evident audit trail.